Resolved
The Joint Committee noted the report, and agreed to approve and re-sign the revised Annual Return for 2017-18
Coychurch Crematorium Joint Committee noted this item on Friday 14 September 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
The Joint Committee noted the report, and agreed to approve and re-sign the revised Annual Return for 2017-18
1.1The purpose of this report is to inform the Joint Committee of details of income and expenditure for the first quarter of the 2018 -19 financial year, and give a projection of the final outturn.
2. Connection to Corporate Improvement Objectives and Other Corporate Priorities
2.1None.
3.1Revenue Estimates for 2018-19 were approved by the Joint Committee at its meeting of 9 March 2018 and the following statement shows the current position.
4. Current Situation / Proposal
4.1Table 1 below shows detail of income and expenditure for April to June 2018 together with the projected outturn for the financial year. Table 1 – Crematorium Financial Position 2018-19
* Adjusted Actual Projected Actual 01/04/2018 Projected Over/ Spend Budget to Outturn (Under) 2017-18 2018-19 30/06/2018 2018-19 Spend £'000 £'000 £'000 £'000 £'000 Expenditure 288 Employees 313 74 309 (4) 224 Premises 234 68 238 4 Supplies, Services & 163 135 60 149 14 Transport 86 Agency / Contractors 102 24 102 0 34 Administration 35 9 35 0 352 Capital Financing 75 0 70 (5) 1,147 Gross Expenditure 894 315 902 8 Income (1,296) Fees & Charges (1,238) (201) (1,295) (57) (28) BCBC Contribution (29) (7) (29) 0 (1,324) Gross Income (1,267) (208) (1,324) (57) (177) Surplus(-)/Deficit (373) 107 (422) (49) (177) Transfer (to)/from Reserve (373) 107 (422)
*Adjusted to include pro-rata commitments during the year.
An explanation of the variances between the Budget and Projected Outturn is detailed below:
The Staffing projected outturn underspend of £4,000 is as a result of one Weekend Assistant position being vacant.
The Premises projected outturn overspend of £4,000 is made up of overspends on Electricity (£2,000), Water (£1,500) and Contract Cleaning (£600).
The Supplies, Services & Transport projected outturn overspend of £14,000 is made up of an overspend on Equipment Repairs & Maintenance (£15,000) which is offset by an underspend on Insurance (£1,000).
The projected additional Fees & Charges income of £57,000 is made up of Cremation Fees (£52,000) and the Child Burial Fees Grant from Welsh Government (£5,000).
4.2The Capital Financing budget of £75,000 is broken down in the table below. Table 2 – Capital Works Budget 2018-19
Projected Budget Spend to Outturn 2018-19 30 June 2018-19 2018-19 £ 000 £ 000 £ 000 Organ upgrade 20 0 20 Phase 2, Land Extension Retention 5 0 0 Flat Roof Repairs – Waiting Room 30 0 30 Chapel of Remembrance Repairs 20 0 20 Total 75 0 70
The projected underspend of Capital Works is due to the Phase 2 Land Extension retention being paid at the end of the 2017-18 financial year, and is included in the 2017-18 spend of £352,000.
Annual Return
4.3The Annual Return for 2017-18 (Appendix 1) was submitted to Wales Audit Office at the end of June 2018, showing a surplus of £177,000 for the year, and an accumulated balance of £1,259,000. Wales Audit Office has now written to confirm that the Return has been audited (Appendix 2).
There was an error in the 2016-17 comparative figure for total borrowing, which showed a figure of £79,784 instead of £78,784. This figure was for comparison purposes only, and does not affect the 2017- 18 figures. As the report has been amended, the return needs to be approved and re-signed by the Committee. A copy of the certified return will be made available at the Crematorium and electronically on the Bridgend CBC website.
5. Effect upon Policy Framework and Procedure Rules
5.1There is no impact on the Policy Framework and Procedure Rules. .
6. Equalities Impact Assessment
6.1There are no equality implications arising from this report.
7 Well-being of Future Generations (Wales) Act 2015 Implications
7.1This report provides the financial performance against the approved 2018-19 budget. As this is retrospective in nature, there is no requirement for a well-being statement.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Coychurch Crem revised 3-9Appendix 1 | 560 KB | Download |
PDF |
DO18-011 Coychurch Crem Cttee Annual ReturnAppendix 2 | 157 KB | Download |
PDF |
Revenue Monitoring Statement 1 April to 30 JuneReport | 69 KB | DownloadRead as text |
Follow Coychurch Crematorium Joint Committee at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2023 | Approval of MinutesThat the minutes of a meeting of the Coychurch Crematorium Joint Committee dated 9 June 2023, be approved as a true a... | Approved | Open |
| 1 Sep 2023 | Green Flag AwardThe Committee thanked the staff and management at Coychurch Crematorium for their continued hard work and stewardship... | Noted | Open |
| 1 Sep 2023 | Revenue Monitoring Statement 1 April to 30 June 2023 & Annual Accounting Statement 2022-23 updateThe Committee noted and approved the Revenue Monitoring Statement, noting that there is considerable value for money ... | Noted | Open |
| 1 Sep 2023 | Urgent ItemsNone | Decided | Open |
| 9 Jun 2023 | Election of Chairperson (from Rhondda Cynon Taf County Borough Council members)That Councillor B Stephens be appointed as Chairperson of the Coychurch Crematorium Joint Committee for the ensuing y... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.