That Cabinet: (1) Approved the decision to implement an Air Quality Management Area (AQMA) on Park Street based on the evidence provided. (2) Approved the detail of the proposed AQMA Order, as attached in Appendix 2 for submission to Welsh Government and to be made publically available. (3) Approved the decision to undertake a public engagement exercise with impacted residents and businesses, prior to the implementation of the AQMA Order. That a further report be awaited on this matter in due course.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1Supported by the evidence outlined in the Technical Note, attached at Appendix 1, the purpose of the report is to seek Cabinet approval for an Air Quality Management Area (AQMA) designation order for Park Street, Bridgend. Cabinet is required to approve the designation of the AQMA order prior to a final version being submitted to Welsh Government, and the order made publically available.
1.2To approve a public engagement exercise with impacted residents and businesses prior to the implementation date of 1st January 2019.
2. Connection to corporate improvement objectives/other corporate priorities
2.1This report assists in the achievement of the following corporate priority/priorities:
Supporting a successful economy – taking steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county.
Background
3.1Under Section 82 of the Environment Act 1995 every local authority has an obligation to regularly review and assess air quality in their areas, and to determine whether or not air quality objectives to protect health are likely to be achieved. Where the air quality reviews indicate that the air quality objectives are not being achieved, or are not likely to be achieved, Section 83 of the 1995 Act requires local authorities to designate an Air Quality Management Area (‘AQMA’). Section 84 of the Act ensures that action must then be taken at a local level which is outlined in a specific Air Quality Action Plan (AQAP) to ensure that air quality in the identified area improves.
3.2There are currently 30 specifically allocated non automatic monitoring sites in Bridgend which monitor levels of Nitrogen Dioxide (NO2). These sites are supported and maintained by SRS on behalf of BCBC. The non-automatic sites do not provide live data; instead they consist of diffusion tubes which are placed at each of the sites, collected and replaced on a rolling monthly basis. The results derived from the tube sampling are then averaged over the year to enable a comparison of the results against the annual mean (40µg/m3) and 1-hour mean (200µg/m3 not to be exceeded > 18 times per year) air quality objectives for NO2.
4. Current situation/proposal
4.1On 18th September 2018 BCBC’s Cabinet approved the 2018 Local Air Quality Management Annual Progress Report (APR) for Bridgend, as produced by SRS on behalf of BCBC. The report examined datasets captured during 2017 and noted that Park Street, Bridgend was an area of particular concern and subsequently an Air Quality Management Area (AQMA) was required.
4.2It was reported that two nitrogen dioxide (NO2) monitoring locations situated at residential facades on Park Street, as displayed by Figure 1 and Table 1 recorded elevated and exceeding annual average levels of NO2 when compared to the annual mean NO2 Air Quality Objective of 40µg/m3.
Table 1- 2017 Annual Mean NO2 Concentrations
Annual Mean Concentration (µg/m3) AQS = 40 µg/m3 (2) Site ID
4.3For 2018, monitoring for NO2 has been increased further along Park Street, with an additional two NO2 monitoring sites implemented. These will continue to be monitored. Figure 2 illustrates the current 2018 network of monitoring for Park Street including the additional two locations (OBC- 109 and OBC- 110).
Figure 2- 2018 NO2 Diffusion Tube Monitoring Locations, Park Street 4.4 Although a full dataset is not available for 2018, it is evident that the NO2 annual mean objective is likely to be breached, especially at newly commissioned site OBC-110.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.