Resolved
That Cabinet: (1) Noted the outcome of the bid submitted to Welsh Government in respect of the Welsh-medium capital grant bid; and (2) Approved the approach to the scheme development.
Cabinet noted this item on Tuesday 18 December 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet: (1) Noted the outcome of the bid submitted to Welsh Government in respect of the Welsh-medium capital grant bid; and (2) Approved the approach to the scheme development.
1.1The purpose of this report is to:
update Cabinet with regards to the outcome of the bid submitted to Welsh Government in respect of the Welsh-medium capital grant; and
advise on the way forward in respect of the scheme development.
2. Connection to corporate improvement objectives/other corporate priorities
2.1This report relates to the following Corporate Improvement Plan priorities:
Supporting a successful economy - we will take steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county.
Helping people to be more self-reliant – we will take early steps to reduce or prevent people from becoming vulnerable or dependent on the Council and its services.
Smarter use of resources – ensuring that all its resources (financial, physical, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.
3.1In March 2018, the Cabinet Secretary for Finance made available £30m across Wales for projects dedicated to supporting and growing the use of the Welsh language in education. This funding would assist the delivery of Welsh Government’s ongoing commitment to achieve a million Welsh speakers by 2050.
3.2Welsh Government advised that this funding was in addition to the existing allocation announced for Band B of the 21st Century Schools and Education Programme. With this in mind, consideration was given to how best increase the number of Welsh speakers within the borough.
3.3A childcare sufficiency audit of settings within Bridgend had identified gaps in this vital provision. These gaps, together with a lack of Welsh-medium childcare, resulted in a decision being taken to centre Bridgend’s proposals on Welsh-medium sessional, child and wraparound care.
3.4In determining the locations that would benefit from such provision, consideration was given to developing centres to support transition from Welsh-medium childcare provision to Welsh-medium primary education, thereby encouraging transition, and in turn, promoting and supporting Welsh-medium schools in key areas of the county borough.
3.5The Garw Valley South scheme, which is being delivered through Band A of the School Modernisaton Programme, will culminate with the opening of Ysgol Gynradd Gymraeg Calon Y Cymoedd at Bettws, in January 2019. Bettws and Ogmore Valley areas were identified as key locations that would benefit from Welsh-medium childcare provision which would help support transition into the school at its new location.
3.6In addition, the geographical areas of Bridgend Town and Porthcawl were also identified as requiring Welsh-medium childcare settings, which in turn would support transition into Ysgol Gymraeg Bro Ogwr and Ysgol Y Ferch o’r Sgêr respectively.
3.7Therefore, a £2.6m bid was submitted to create Welsh-medium childcare provision in Bettws, Ogmore Valley, Bridgend Town and Porthcawl.
4. Current situation
4.1In September, the Minister for Welsh Language and Lifelong Learning announced the outcome of the bidding process, and Bridgend County Borough Council was awarded a £2.6m capital grant.
4.2Preliminary work has started on developing each of the projects. Two teams have been established (ie a project team and a steering group). The projects will be managed by project managers within the School Modernisation Team. The School Modernisation Programme Board will support the projects offering advice and guidance.
4.3The project team will deliver the construction element of the scheme and work has commenced on the initial stages of the project focusing on options appraisal in respect of developable land.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Welsh: Medium Capital GrantReport | 113 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.