CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Bridgend County Borough Council
Cabinet, Tuesday 16 April 2019

Smart Energy Plan - Domestic Energy Efficiency Project

Approved Executive 1 paper

Cabinet approved this item on Tuesday 16 April 2019. Below is the council's own wording, with the papers it was decided on.

Item349

Resolved

That Cabinet approved the participation of BCBC in, and the development of, a WG funded domestic energy efficiency project under Phase 3 of the domestic energy efficiency programme within Bridgend County Borough.
Word for word from the decision Bridgend published for this meeting. Source: democratic.bridgend.gov.uk

Follow this further

Built from Bridgend's papers

What the report saysPro

Report to Cabinet

BRIDGEND COUNTY BOROUGH COUNCIL

REPORT TO CABINET

16 APRIL 2019

REPORT OF THE CORPORATE DIRECTOR - COMMUNITIES

SMART ENERGY PLAN – DOMESTIC ENERGY EFFICIENCY PROJECT

1. Purpose of Report.

1.1The purpose of this report is to present to, and seek approval from, Cabinet for Bridgend County Borough Council’s support for a Welsh Government project to improve the energy efficiency of domestic properties within Bridgend County Borough.

2. Connection to Corporate Improvement Objectives/Other Corporate Priorities

2.1This report assists in the achievement of the following corporate priority/priorities:-

1. Supporting a successful economy – taking steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county.

2. Smarter use of resources – ensuring that all its resources (financial, physical, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.

3. Background.

3.1Welsh Government (WG) has operated domestic energy efficiency programmes since 2009. The initial programme ran from 2009 – 2011 and involved a £30m investment from WG which enabled a further £31m to be leveraged from Registered Social Landlords (RSLs) and energy supply companies. Measures were funded and installed in over 6,000 homes across Wales through Phase 1.

3.2A Phase 2 programme ran from 2012 – 2016 and had a total value of £45m. The programme was partly funded by the European Regional Development Fund (ERDF) (£33m) and partly funded by WG (£12m). In 2014/15 WG invested a further £22m alongside the existing ERDF funding to install measures in 6,535 homes across Wales.

3.3A Phase 3 programme will run from 2018 – 2021 and seeks to invest £54m over this period into over 6,000 homes in areas where fuel poverty is prevalent. The funding for the programme will come from ERDF, WG and energy supply company sources through the Energy Company Obligation (ECO). 3.4 The primary focus of the programme is to reduce fuel poverty. A home is considered to be in fuel poverty if they spend more than 10% of their household income on energy and in severe fuel poverty if they spend more than 20% of their total household income on energy.

4. Current situation / proposal.

4.1The Phase 3 Programme will be delivered by Arbed am Byth, which is a joint venture company between Everwarm and the Energy Saving Trust. Arbed am Byth will work with BCBC, building on the existing partnership approach to deliver the Smart Energy Plan, to identify areas of fuel poverty where the programme could have maximum impact. Arbed am Byth, as the Scheme Manager, will manage the programme from the beginning to the end and will identify and develop the schemes through the development of local relationships with stakeholders and supply chains.

4.2The Scheme Manager will identify the areas to be targeted through the use of data sources such as:

 Welsh Index of Multiple Deprivation (WIMD)  Energy Performance Certificates (EPC)  Lower Super Output Area (LSOA) data  Housing Benefit Data  Flying Start Areas  Free School Meals Data  Housing and Health Action Data

4.3To date the Scheme Manager has carried out a high level mapping exercise of potential areas within Bridgend County Borough where the Welsh Government Programme could have maximum impact and two areas have been identified (these will require further discussion to agree actual boundaires and areas to be considered). The two initial areas identified are:

 Western sector of the County Borough (Kenfig Hill, Cornelly, Pyle, Cefn Cribwr),  Bridgend Town (Morfa)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Smart Energy Plan: Domestic Energy Efficiency ProjectReport 85 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 12 attended
GL
Gill LewisOfficer, in attendance
KW
Kelly WatsonOfficer, in attendance
CH
Cynghorydd Huw DavidChairperson, present
CC
Cynghorydd Charles SmithCommittee Member, present
CP
Cynghorydd Philip WhiteCommittee Member, present
CH
Cynghorydd Hywel WilliamsCommittee Member, present
MS
Mark ShephardOfficer, in attendance
SC
Susan CooperOfficer, in attendance
LH
Lindsay HarveyOfficer, in attendance
CD
Cynghorydd Dhanisha PatelCommittee Member, present
CR
Cynghorydd Richard YoungCommittee Member, present
ZS
Zak ShellOfficer, in attendance

On this subject at Bridgend

Search all
  1. Smart Energy Plan - Domestic Energy Efficiency ProjectThis decision
  2. Local Area Energy Strategy and Smart Energy PlanApproved

More from Bridgend Cabinet

All decisions
MeetingDecisionOutcome
17 Oct 2023 Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... Noted Open
17 Oct 2023 Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... Noted Open
17 Oct 2023 Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... Noted Open
17 Oct 2023 Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... Approved Open
17 Oct 2023 Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies