Resolved
That the Joint Committee ; (1) approved the proposed design of the extension to the Flower Court Facility authorised the technical officer to seek planning permission and invite tenders in ... view the full minutes text for item 56.
Coychurch Crematorium Joint Committee approved this item on Friday 14 June 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Joint Committee ; (1) approved the proposed design of the extension to the Flower Court Facility authorised the technical officer to seek planning permission and invite tenders in ... view the full minutes text for item 56.
1.1The purpose of this report is to update the Joint Committee on the provision of an extension to the Flower Court facility at Coychurch Crematorium and to seek approval for the design.
2. Connection to Corporate Improvement Objectives/Other Corporate Priorities
2.1This report assists in the achievement of the following corporate priorities:-
1. Supporting a successful economy – taking steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county.
2. Helping people to be more self-reliant – taking early steps to reduce or prevent people from becoming vulnerable or dependent on the Council and its services.
3. Smarter use of resources – ensuring that all its resources (financial, physical, human and technological) are used as effectively and efficiently as possible and support the development of resources throughout the community that can help deliver the Council’s priorities.
3.1The buildings of the Crematorium are carefully designed to provide for the ceremonial and sacred aspects of the cremation service and to complement the landscape in which they sit. The Crematorium is an important work by a British architect of international reputation (Maxwell Fry) and is Grade 2* listed. As such, any proposed changes to the scheme must be carefully considered.
3.2The Crematorium is regularly complemented by service users for the high standard of facilities provided and this is evident on the returned service questionnaires. The Flower Court facility, however, is an area that lends itself to improvement due to its compact layout. It is proving inadequate for the functions it is required to accommodate. 3.3 An area of open grass immediately joins the Flower Court area and provides additional space that could facilitate the construction of a purpose made extension to join the existing facility, to create one much larger flower display and dispersal area.
3.4At the site visit to the Crematorium, in advance of the meeting of 15 th June 2018, Members were shown the Flower Court facilities to the rear of the Crematorium building where the bereaved families greet their congregation and view their floral tributes following the funeral service in the Crallo Chapel. The Flower Court is accessed via a set of doors at the front of the chapel and comprises of a narrow corridor with toilet facilities on one side and the raised flower display to the other. An open section at the far end of the corridor leads to the waiting funeral cars and main car park. Members were reshown these facilities at the site visit to the Crematorium in advance of today’s meeting.
3.5An explanation was provided of the bottleneck that is created when large congregations file through one set of doors and into the limited space of the Flower Court. Additionally, the delay that can be caused to the following funeral service as a result of the slow movement of the congregation through this area.
3.6At the meeting on 15th June 2018 the Joint Committee approved, in principle, the provision of an extension to the Flower Court facility by extending the rear of the Crematorium building, outside the exit doors of Crallo Chapel. The Joint Committee authorised the submission of a feasibility report to a future meeting.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Flower Court FacilitiesReport | 79 KB | DownloadRead as text |
PDF |
JC Report June 19: TechOfficer-FlowerCourtFacilities-AppendixAiiAppendix | 650 KB | Download |
PDF |
JC Report June 19- TechOfficer-FlowerCourtFacilities-AppendixAiAppendix | 68 KB | Download |
Follow Coychurch Crematorium Joint Committee at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Sep 2023 | Approval of MinutesThat the minutes of a meeting of the Coychurch Crematorium Joint Committee dated 9 June 2023, be approved as a true a... | Approved | Open |
| 1 Sep 2023 | Green Flag AwardThe Committee thanked the staff and management at Coychurch Crematorium for their continued hard work and stewardship... | Noted | Open |
| 1 Sep 2023 | Revenue Monitoring Statement 1 April to 30 June 2023 & Annual Accounting Statement 2022-23 updateThe Committee noted and approved the Revenue Monitoring Statement, noting that there is considerable value for money ... | Noted | Open |
| 1 Sep 2023 | Urgent ItemsNone | Decided | Open |
| 9 Jun 2023 | Election of Chairperson (from Rhondda Cynon Taf County Borough Council members)That Councillor B Stephens be appointed as Chairperson of the Coychurch Crematorium Joint Committee for the ensuing y... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.