The Chairperson accepted the Development Control Committee Amendment Sheet as an urgent item in accordance with Part 4 (paragraph 4) of the Council Procedure Rules, in order to allow for the Committee to consider necessary modifications to the Committee report, so as to take account of late representations and revisions that are required to be accommodated.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
AMENDMENT SHEET The Chairperson accepts the amendment sheet in order to allow for Committee to consider necessary modifications to the Committee report to be made so as to take account of late representations and corrections and for any necessary revisions to be accommodated.
ITEM NO. PAGE NO. APPLICATION NO.
8 13 P/19/466/BCB
A Full Committee Site Visit was undertaken on 23 October 2019.
The Ward Member, Cllr. Lyn Walters, a representative from Bridgend Town Council, (Town Cllr. David Unwin) and a representative of the applicant department (Jason Burton - Principal Architectural Assistant) attended the site visit.
During the discussions, Cllr Lyn Walters sought clarification on the access arrangements to the hub during the school holidays and referenced an emailed communication sent to one of the objectors which indicated that, during the longer school holidays, the Brynteg Gardens access would be closed with access to the hub being provided off Ewenny Road for that period.
This arrangement is broadly acceptable but will need to form part of the overall management plan that will be submitted, agreed and reviewed in discharge of condition 10. The Education Section and the Head Teacher remain committed to accommodating the residents’ wishes in regard to the access arrangements.
Condition 1 of the consent should be re-worded to take account of the recommendations in the Ecological Impact Assessment undertaken by Wildwood Ecology:
1. The development shall be carried out in accordance with the following approved plans and documents:-
A001 – Site Location Plan A002 – Topographical Survey A003 – Demolition and Clearance A004 – Site Sections A101 – Proposed Site Layout – Revision A A104 – Proposed Plans and Elevations
The Conclusions and Recommendations in the Ecological Impact Assessment undertaken by Wildwood Ecology dated 18 October 2019.
Reason: To avoid doubt and confusion as to the nature and extent of the approved development.
Condition 12 should be amended and the following additional point should be added:
viii. no lorries associated with the construction of the site entering or leaving the site during the periods of half hour either side of the times school commencing and ending and contact being made with the Head Teacher of Brynteg Comprehensive School in order to make the school aware of the additional traffic movements.
9 31 P/19/550/FUL
Condition 4 should include the following words: “… including the removal of the hub container office.” 10 47 P/19/316/FUL
As Ownership Certificate B has now been completed and Notice was only served on the adjoining occupier (2 Williams Terrace) on 13 October, 2019, the 21 day notice period will not elapse until 3 November 2019.
However, the adjoining occupier is aware of the application and has provided comments which have been summarised and addressed in the report.
Although the adjoining occupier has not been prejudiced by the lack of notification by the applicant, in order to satisfy the requirements of Article 10 of the Development Management Procedure (Wales) Order 2012, the decision cannot be issued until the 21 day notice period has elapsed.
Therefore, the recommendation should be amended to read:
That permission be GRANTED and delegated powers be granted to the Group Manager – Planning and Development Services to issue a decision notice after 4 November, 2019, subject to the following conditions:-
11 63 P/17/369/RLX
Communications have been received from a representative of Llangan Community Council and a local resident concerned that little time has been afforded to arrange for persons to attend and speak at the Development Control Committee. The agenda is however finalised the Friday before committee and this is the date that the notification letters are sent in respect of all Development Control Committee items.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.