Coastal Protection Engineering works to Western Breakwater and Eastern Promenade, including Rhych Point, Porthcawl

Approved Executive 2 papers

Cabinet approved this item on Tuesday 25 February 2020. Below is the council's own wording, with the papers it was decided on.

Item481

Resolved

That Cabinet approved authorisation to tender for the coastal defence work to the Western Breakwater and Eastern Promenade structures and subsequently to award the most economically advantageous tender.
Word for word from the decision Bridgend published for this meeting. Source: democratic.bridgend.gov.uk

Follow this further

Built from Bridgend's papers

What the report saysPro

Report to Cabinet

BRIDGEND COUNTY BOROUGH COUNCIL

REPORT TO CABINET

25 FEBRUARY 2020

REPORT OF THE HEAD OF OPERATIONS -- COMMUNITY SERVICES

COASTAL PROTECTION ENGINEERING WORKS TO WESTERN BREAKWATER AND EASTERN PROMENADE, INCLUDING RHYCH POINT, PORTHCAWL

1. Purpose of Report.

In accordance with procurement rules to seek the approval of Cabinet to invite tenders for coastal defence work to the Western Breakwater and Eastern Promenade, Porthcawl that are estimated to be in excess of £5 million.

2. Connection to Corporate Improvement Objectives / Other Corporate Priorities

2.1This report assists in the achievement of the following corporate priority:-

Supporting a successful economy – taking steps to make the county a good place to do business, for people to live, work, study and visit, and to ensure that our schools are focused on raising the skills, qualifications and ambitions of all people in the county

3. Background.

3.1Western Breakwater, Eastern Promenade and Rhych Point are covered by the South Wales (Lavernock Point to St. Ann’s Head) Shoreline Management Plan 2 (SMP2), inside Policy Scenario Unit 7. The SMP2 states that “the main policy driver for this frontage is to reduce the risk of coastal erosion and flooding to the developed area of Porthcawl, through a policy of hold the line by maintaining and upgrading defences at Trecco Bay, Sandy Bay, Town Beach and Marine Drive, subject to the future availability of public funding for coastal erosion and flood risk management”.

3.2The Western Breakwater was constructed in the 1820s, with a further extension in the 1860s. The sea wall at Eastern Promenade was constructed in the 1860s, to form part of the inner harbour. The Western Breakwater and Eastern Promenade sea walls have been successful in protecting the seafront properties against flooding and erosion. The Outline Business Case has identified that the sea wall structures are reaching the end of their life and becoming more susceptible to overtopping and ongoing maintenance requirements and costs will increase exponentially over the next decade. It is considered that the works future proof the structure for the long term which along with appropriate maintenance would meet the timeline of 50-100 years, in relation to requirements of epoch 3 in SMP2.

3.3The sea wall and breakwater structures generally have re-pointing works undertaken funded from its annual budget allocation. This only provides a basic level of maintenance to the outer shell of the structures and does not address any internal structural and hydrology issues. The Western Breakwater has been subject to historic failures, most notably in 1974 when the inner old wall collapsed following storm damage, which caused deck surcharge loads and storm washout, and ultimately led to a collapse/failure of the Eastern end of the structure.

3.4The need to provide continuing flood and coastal erosion defence to the sea-front is recognised in the SMP2 and the Council carries out regular inspections of the structures carrying out holding repairs as required to reduce the likelihood of catastrophic failure. See appendix 1: site location boundary for all areas of inclusion within the scheme.

3.5The asset inspection of the Western Breakwater undertaken in March 2017 identified that this Breakwater was in a deteriorating condition warranting intervention.

3.6The structures protect several million pounds worth of assets and infrastructure along the Western Breakwater and Eastern Promenade including; the walkways, highway, commercial businesses and the properties within the Jennings building and properties that would otherwise be impacted by flooding events from the Porthcawl seafront.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Site Boundary Eastern Prom: Western BreakwaterAppendix 1 333 KB Download
PDF
Coastal Protection Engineering works to Western Breakwater and Eastern Promenade, including Rhych Point, PorthcawlReport 83 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

4 of 22 attended
R-
Room - Committee Room 1Officer, expected
R-
Room - Committee Room 2Officer, expected
R-
Room - Committee Room 3Officer, expected
RR
Ruth RonanOfficer, expected
GL
Gill LewisOfficer, in attendance
KW
Kelly WatsonOfficer, in attendance
LK
Laura KinseyOfficer, expected
CH
Cynghorydd Huw DavidChairperson, present
CC
Cynghorydd Charles SmithCommittee Member, present
CP
Cynghorydd Philip WhiteCommittee Member, present
CH
Cynghorydd Hywel WilliamsCommittee Member, apologies
MS
Mark ShephardOfficer, in attendance

All 22 on the meeting page

More from Bridgend Cabinet

All decisions
MeetingDecisionOutcome
17 Oct 2023 Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... Noted Open
17 Oct 2023 Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... Noted Open
17 Oct 2023 Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... Noted Open
17 Oct 2023 Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... Approved Open
17 Oct 2023 Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies