P/19/911/RLX - Land At Moor Lane, Porthcawl

Agreed Planning 1 paper

Development Control Committee agreed this item on Thursday 27 February 2020. Below is the council's own wording, with the papers it was decided on.

Item365

Resolved

That the above application be granted, subject to the Conditions contained in the report of the Corporate Director – Communities:- Proposal Vary conditions 1, 3, 8, 9, 10, 11, 12, 13 14, 18, 19, 23 and 24 of P/19/115/RLX to facilitate an increased provision of timber chalet accommodation units from 56 to 80. Condition 13 should now read:- 13. Within six months of the date of this consent, an updated Traffic & Delivery Management Plan for the site shall be submitted to and agreed in writing by the Local Planning Authority. All guest arrivals and departures and servicing and delivery vehicles movements to the site shall be made in accordance with the agreed Traffic & Delivery Plan once the development is brought into beneficial use. Reason: In the interests of highway safety. As a result, advisory note g. at the end of the recommendation should be changed to refer to Condition 13, not 10 as follows: g. The Traffic and Delivery Management Plan required to address Condition 13 will need to contain sufficient information in respect of the following:- (i) Guest arrival and departure arrangements (directions to the site and timing of those movements; (ii) Guest arrival and departures of the adjacent Brodawel Caravan Park; (iii) Proposed Delivery Schedules; (iv) Proposed Delivery Vehicle/Service Vehicles sizes; (v) Supporting swept path diagrams; and (vi) The need to review the plan in the event that any of the above arrangements change or at the request of the Highway Authority. Condition 22 of the recommendation should be superseded by the following wording: 22. Site clearance works shall be taken in full accordance with:- · The details relating to lighting design, method for vegetation clearance, knotweed protocol as approved under App. No. P/18/827/DOC dated 15th February, 2019. · The pollution prevention measures which comprise a 5m wide buffer zone from the SINC along with a 2m x 1m clay bund as approved under App. No. P/19/307/DOC dated 31 st May, 2019. Reason: In the interests of biodiversity. Subject to the inclusion of a further Condition 25 as follows:- 25. Prior to the beneficial occupation of the holiday chalets, a scheme for the provision of gateway traffic signs warning of the presence of equestrians sharing the highway at the junction of Moor Lane with the A4229 and the junction of Moor Lane near St. David’s Well to the east and at the junction of Moor Lane opposite Parc Newydd Farm Caravan Site to the west, together with any necessary illumination, shall be submitted to and agreed in writing by the Local Planning Authority. The approved scheme shall thereafter be implemented in accordance with the approved details prior to the development being brought into beneficial use and shall thereafter be maintained in perpetuity. Reason: In the interests of highway safety. In addition, the following original Condition should be included under the recommendation: 26. All site clearance works shall be undertaken in accordance with the methods and measures contained within the Mitigation Method Statement - Great Crested Newt prepared by Soltys ... view the full minutes text for item 365.
Word for word from the decision Bridgend published for this meeting. Source: democratic.bridgend.gov.uk

Follow this further

Built from Bridgend's papers

What the report saysPro

Report to Development Control Committee

REFERENCE: P/19/911/RLX APPLICANT: Ward Jones (Bridgend) Ltd. c/o John Matthews Development Consultant, 47 Anglesey House, Anglesey Way, Nottage CF36 3QP LOCATION: Land at Moor Lane, Porthcawl CF36 3EJ PROPOSAL: Vary conditions 1, 3, 8, 9, 10, 11, 12, 13, 14, 18, 19, 23 and 24 of P/19/115/RLX to facilitate an increased provision of timber chalet accommodation units from 56 to 80 RECEIVED: 06 December 2019

APPLICATION/SITE DESCRIPTION The application seeks to vary conditions 1, 3, 8, 9, 10, 11, 12, 13, 14, 18, 19, 23 and 24 of P/19/115/RLX to allow an increase in the number of timber chalet accommodation units on the site from 56 to 80. The original consent (P/16/497/FUL) related to the change of use of the land for the provision of high quality self-catering mobile wooden chalet tourist accommodation units and supporting facilities and that application was reported to DC Committee in April 2017.

The relevant conditions and proposed changes are as follows:

1. The consent hereby approved shall be limited to the siting of 56 timber chalet accommodation units, which shall be mobile, not fixed to the ground laid out in accordance with the 1:1250 scale Site Plan received on 11th October, 2018 and submitted as part of the discharge of condition application P/18/827/DOC and in accordance with the 1:100 scale plans of the 3 bed, 2 bed and smaller 2 bed timber units received on 11th October, 2018 and submitted as part of the discharge of condition application P/18/827/DOC together with the 1:200 scale plan of the Service Centre Building received on 11th October, 2018 and submitted as part of the discharge of condition application P/18/827/DOC.

The applicant seeks the following amendment to the condition:-

The consent hereby approved shall be limited to the siting of 80 timber chalet accommodation units, which shall be mobile, not fixed to the ground laid out in accordance with the revised 1:1250 scale Site Plan received on 6th December 2019 and in accordance with the 1:100 scale plans of the 3 bed, 2 bed and smaller 2 bed timber units received on 11th October, 2018 and submitted as part of the discharge of condition application P/18/827/DOC together with the 1:200 scale plan of the Service Centre Building received on 11th October, 2018 and submitted as part of the discharge of condition application P/18/827/DOC.

3. This consent permits the year round occupation of the timber chalet units but no unit shall be occupied as a person's or persons' place of residence nor shall any unit be occupied by the same person or persons for a period exceeding 42 days between April and September (inclusive) and 42 days between October and March (inclusive).

The applicant seeks the following amendment to the condition:-

This consent permits the year round occupation of the timber chalet units but no unit shall be occupied as a person's or persons' place of residence nor shall any unit be occupied by the same person or persons for a period exceeding 28 days within any 12 month period. 8. No development shall take place, including any works of site clearance, until a Construction Method Statement has been submitted to, and approved in writing by the Local Planning Authority. The approved Method Statement shall be adhered to throughout the site clearance and construction period. The Statement shall provide for:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
P/19/911/RLX: Land At Moor Lane, PorthcawlReport 353 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 26 attended
CJ
Cynghorydd Jon-Paul BlundellCommittee Member, present
CN
Cynghorydd Nicole BurnettCommittee Member, present
CR
Cynghorydd Richard CollinsCommittee Member, apologies
RD
Rhodri DaviesOfficer, in attendance
CS
Cynghorydd Sorrel DendyCommittee Member, present
CK
Cynghorydd Keith EdwardsCommittee Member, present
CF
Craig FlowerOfficer, in attendance
MG
Mark GalvinOfficer, in attendance
CR
Cynghorydd Richard GranvilleCommittee Member, present
RJ
Rod JonesOfficer, in attendance
CM
Cynghorydd Mike KearnCommittee Member, apologies (other personal or family responsibilities)
HK
Hayley KempOfficer, in attendance

All 26 on the meeting page

On this subject at Bridgend

Search all
  1. P/19/911/RLX - Land At Moor Lane, PorthcawlThis decision
  2. P/22/588/RLX - St. Johns School, Church Street, Newton, Porthcawl, CF36 5SJ - Variation of condition 1 of P/21/211/RLX – tree removal/tree retention plans & landscaping schemeAgreed
  3. P/20/888/RLX - Land Off All Saint's Way, Penyfai, CF31 4BXAgreed
  4. P/20/285/RLX - Land At The Former Playground, Fountain Road, CF31 3XUApproved
  5. P/19/674/RLX - Land Off Parc Crescent, Waterton Industrial Estate (Storewithus), CF32 0EWDecided
  6. P/17/369/RLX - Land off Horsefair Road, Waterton Industrial Estate, Bridgend, CF31 3YNAgreed

More from Bridgend Development Control Committee

All decisions
MeetingDecisionOutcome
19 Oct 2023 Site VisitsThat a date for any site visits agreed by the Committee or identified in advance of the next meeting by the Chairpers... Agreed Open
19 Oct 2023 Approval of MinutesThat the Minutes of a meeting of the Development Control Committee dated 7 September 2023, be approved as a true and ... Approved Open
19 Oct 2023 Amendment SheetThe was accepted by the Chairperson as an urgent item under Part 4, paragraph 4 of the Council Procedure Rules. Decided Open
19 Oct 2023 Development Control Committee GuidanceThat the report of the Corporate Director – Communities, outlining the be noted. Noted Open
19 Oct 2023 P/23/147/FUL - Rear of 82 Merthyr Mawr Road, Bridgend, CF31 3NSThat the above application be granted, subject to the Conditions contained in the report of the Corporate Director – ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies