Resolved
That the Development Control Committee noted the Regional Technical Statement that will be reported to Council for endorsement.
Development Control Committee noted this item on Thursday 29 October 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Development Control Committee noted the Regional Technical Statement that will be reported to Council for endorsement.
1.1The purpose of this report is to seek endorsement of the Regional Technical Statement in order to meet the requirements of National Planning Policy and agree the progression of the Statement of Sub-Regional Collabration.
2. Connection to corporate well-being objectives/other corporate priorities
2.1This report assists in the achievement of the following corporate well-being objective/objectives under the Well-being of Future Generations (Wales) Act 2015:-
1. Supporting a successful sustainable economy – taking steps to make the County Borough a great place to do business, for people to live, work, study and visit and to ensure that our schools are focussed on raising the skills, qualifications and ambitions for all people in the County Borough.
2. Smarter use of resources – ensure that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the creation of resources throughout the community that can help to deliver the Council’s well-being objectives.
3.1Minerals Technical Advice Note 1: Aggregates (2004) (MTAN 1) requires the preparation of Regional Technical Statements (RTS) for the areas covered by both the South Wales and North Wales Regional Aggregates Working Parties (RAWPs). The original RTS documents for both regions were completed in 2008 and are required by MTAN 1 to be reviewed every five years. The First Review was undertaken in 2013/2014 and this the Second Review commenced in 2018.
3.2The methodology used in the previous (First) Review in 2014 had been based primarily on historical sales averages combined with an assessment of the various ‘drivers’ of potential future change. For the Second Review this has been combined with an attempt to reflect planned future requirements for housing construction activity and to avoid perpetuating historical supply patterns in areas where there is scope to encourage more sustainable patterns of supply. 3.3 The change in methodology means that Bridgend is required through its Local Development Plan process to meet the apportionment set out in the RTS. For Bridgend this requirement is set at 17.471MT of crushed rock for the LDP period (an explanation of the calculations are set out in Section 4). The Authority currently has zero existing landbanks for sand and gravel and 27.27MT for crushed rock (as at 31 December). The RTS requires the apportionment to be met through the allocation of Specific Sites or failing that, Preferred Areas. If as a last resort it is only possible to identify broad Areas of Search, these should be sufficient to offer the potential of much greater quantities of reserves in order to reflect the uncertainties involved. If it is not possible for Bridgend to meet this requirement, then a sub-regional approach is required. Bridgend has been grouped with Cardiff, the Vale of Glamorgan, Rhondda Cynon Taf, Merthyr Tydfil, Caerphilly and the Brecon Beacons National Park. To satisfy this requirement several stages will need to be undertaken (set out in Figure 1), the outcome of which will be a Statement of Sub-Regional Collaboration.
STAGE 1 If stage 1 evidences that If stage 2 evidences that there isnt capacity in there isnt capacity in Cardiff Examine capacity within Bridgend to meet the City sub-region to meet the Bridgend for meeting apportionment then: apportionment then: apportionment e.g. through engagement with industry STAGE 2 STAGE 3 This may not be possible due Identify an alternative Identify an alternative to the lack or insuffient supply from the Cardiff City supply from a neighbouring workable agrregage authorities sub-regional authority resource or no interest form the industy.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Endorsement of Regional Technical Statement 2020Report | 7.7 MB | DownloadRead as text |
Follow Development Control Committee at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 19 Oct 2023 | Site VisitsThat a date for any site visits agreed by the Committee or identified in advance of the next meeting by the Chairpers... | Agreed | Open |
| 19 Oct 2023 | Approval of MinutesThat the Minutes of a meeting of the Development Control Committee dated 7 September 2023, be approved as a true and ... | Approved | Open |
| 19 Oct 2023 | Amendment SheetThe was accepted by the Chairperson as an urgent item under Part 4, paragraph 4 of the Council Procedure Rules. | Decided | Open |
| 19 Oct 2023 | Development Control Committee GuidanceThat the report of the Corporate Director – Communities, outlining the be noted. | Noted | Open |
| 19 Oct 2023 | P/23/147/FUL - Rear of 82 Merthyr Mawr Road, Bridgend, CF31 3NSThat the above application be granted, subject to the Conditions contained in the report of the Corporate Director – ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.