Resolved
That Cabinet approved the modification of the bus service contract in accordance with CPR 3.3.6 to allow for a 12 month extension of the contract for Service No. 65 and Service No. 70 from 01 November 2021.
Cabinet approved this item on Tuesday 19 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet approved the modification of the bus service contract in accordance with CPR 3.3.6 to allow for a 12 month extension of the contract for Service No. 65 and Service No. 70 from 01 November 2021.
1.1The purpose of this report is for Cabinet to approve the modification of an existing contract to allow for a 12 month extension to Service No. 65 (Bridgend to Talbot Green via Heol-y-Cyw) and Service No. 70 (Bridgend to Cymmer via Maesteg) in accordance with Contract Procedure Rule (CPR) 3.3.6.
2. Connection to corporate well-being objectives / other corporate priorities
2.1This report assists in the achievement of the following corporate well-being objective under the Well-being of Future Generations (Wales) Act 2015:
Smarter use of resources – ensure that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the creation of resources throughout the community that can help to deliver the Council’s well-being-objectives.
3.1Bus Service No. 65 and Service No. 70 are funded through the Welsh Governments ‘Bus Services Support Grant’ (BSSG), with the funding administered and distributed by Monmouthshire Council (Lead Authority). Both services are classed as regional bus services, operating into other local authority areas.
3.2This contract was awarded for a 12 month period, and started on 01 November 2016 to 31 October 2017 (with options to extend for periods of up to Twelve (12) months each, and up to a maximum extension period available of Forty Eight (48) months).
3.3The current contract is due to expire after 31 October 2021.
4. Current situation / proposal
4.1Bus travel has been severely affected by the Covid-19 pandemic with passenger numbers plummeting, whilst social distancing and additional cleansing requirements have placed added burdens and costs on operators. Early engagement was undertaken with the Corporate Procurement Team to consider available options as to the retendering or extension of the contract. It was identified that the market would be disrupted due to the impact of the pandemic and that the pace of recovery would dictate the appropriate renewal / extension process and a wait and see approach may be appropriate in the first instance. 4.2 During 2021 Welsh Government have stepped in to support the sector with substantial financial assistance. The sector is still trying to recover but the current emergency with restrictions still in place on public transport in Wales, and numbers not recovered to pre pandemic levels, means any current tendering process will be affected by the current restrictions within the sector. Concerns have been raised through ATCO (Association of Transport Co-ordinating Officers) about the current situation with retendering bus services. Reduced patronage following COVID-19 is very likely to increase tendered contract costs significantly in any subsequent procurement processes undertaken in the present circumstances.
4.3To seek to avoid the above it is proposed to extend the current contract for a further 12 months on the basis of the same level of remuneration and during which time the contract will be retendered. It is likely that an indexation increase may be applied during the period, with calculations shared by a neighbouring Authority (Rhondda Cynon Taff County Borough Council), using the most current information supplied by the Confederation of Passenger Transport and the Office of National Statistics.
4.4The Council’s CPR rule 3.3.6 provides that existing contracts may be modified without the requirement for a new procurement procedure:
Where the value of the modification is below both of the following values:—
(i) the relevant applicable financial thresholds contained in the Regulations, and
(ii) 10% of the initial Contract Value for service and supply Contracts and 15% of the initial Contract Value for works Contracts,
provided that the modification does not alter the overall nature of the contract.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Extension To Contract For Bus Services 65 And 70Report | 235 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.