Resolved
That Cabinet approved the contract modification in accordance with rules 3.3.6 and 3.6 of the Council’s Contract Procedure Rules.
Cabinet approved this item on Tuesday 19 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That Cabinet approved the contract modification in accordance with rules 3.3.6 and 3.6 of the Council’s Contract Procedure Rules.
1.1The purpose of this report is to seek Cabinet approval to modify the contract for carriageway resurfacing for works to be undertaken during the financial year 2022/23.
2. Connection to corporate well-being objectives / other corporate priorities
2.1This report assists in the achievement of the following corporate well-being objective under the Well-being of Future Generations (Wales) Act 2015:-
Smarter use of resources – ensure that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the creation of resources throughout the community that can help to deliver the Council’s well-being objectives.
3.1The procurement of resurfacing of the Highway Network was undertaken through South East Wales Highway Framework, via a mini-competition and tender process in March 2021. The procurement exercise was undertaken in conjunction with the Corporate Procurement team. The contract was awarded to Centregreat Limited and runs from April 2021 to March 2022 with an option to extend the contract for a further 12 months to March 2023 on the parties’ mutual agreement. The contract provides the mechanism for the resurfacing of the Carriageway Network in accordance with the allocated Capital and Revenue budgets for Resurfacing (Revenue spend related to 2021-22 only). The total value of the contract is estimated as £5,000,000 over the two financial years.
3.2Significant inflationary pressures in general, and in particular to the oil prices caused by global events, coupled with the UK government increasing National Insurance Contributions for employers to fund a Health and Social Care levy have created a significant cost increase in material, labour and plant (machinery) costs.
4. Current situation / proposal
4.1The contractor for the works has approached the authority in light of exceptional inflationary increases and has requested an uplift to the fee rates to enable them to maintain the same levels of performance during the extension period. The total cost increase sought is being applied to the costs associated with the operations in 2022/23. It equates to a cost increase of 8.93% over the whole term of the contract. 4.2 The contract rates for resurfacing are made up from material, labour, plant and sub-contractor costs (which also have elements of material, labour and plant). Material costs are affected by the increase in oil which is a significant proportion of the tarmacadam material. Labour costs have increased due to the National Insurance employer’s contribution element. Plant usage relieves heavily on diesel and hence fuel cost increases have had a significant effect.
4.3Cardiff City Council Procurement officers who oversee the South East Wales Highway Framework, under which framework this contract was awarded, have confirmed that, further to representation from contractors on the framework, agreement has been made for the submission of increases to the standard rates across the framework.
4.4Rule 3.3.6 of the Council’s Contract Procedure Rules (CPRs) provides that procured contracts may be modified without the requirement for a new procurement procedure where the value of the modification is below both the relevant applicable financial thresholds contained in the Public Contracts Regulations 2015 and below 15% of the initial contract value for works contracts, provided that the modification does not alter the overall nature of the contract.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2020: 2023 Carriageway Resurfacing ProgrammeReport | 242 KB | DownloadRead as text |
Follow Cabinet at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Oct 2023 | Budget Monitoring 2023-24 - Quarter 2 Revenue ForecastThat Cabinet noted the projected revenue position for 2023-24; approved the virements over £100,000 as outlined in pa... | Noted | Open |
| 17 Oct 2023 | Capital Programme Update - Quarter 2 2023-24that Cabinet: noted the Council’s Capital Programme 2023-24 Quarter 2 update to 30 September 2023 (Appendix A). agree... | Noted | Open |
| 17 Oct 2023 | Treasury Management Half Year Report 2023-24that Cabinet: Noted the treasury management activities for 2023-24 for the half year period 1 April 2023 to 30 Septem... | Noted | Open |
| 17 Oct 2023 | Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St... | Approved | Open |
| 17 Oct 2023 | Corporate Plan Delivery Plan TargetsThat Cabinet considered and approve the targets for the Corporate Plan Performance Indicators in Appendix 1. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.