Resolved
The Committee noted the content of the report and the progress made against the 2022-23 Internal Audit Risk Based Plan.
Governance and Audit Committee noted this item on Thursday 28 July 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
The Committee noted the content of the report and the progress made against the 2022-23 Internal Audit Risk Based Plan.
1.1The purpose of the report is to provide members of the Committee with a position statement on progress being made against the audit work included and approved within the Internal Audit Risk Based Plan 2022-23.
2. Connection to corporate well-being objectives / other corporate priorities
2.1This report assists in the achievement of the following corporate well-being objective under the Well-being of Future Generations (Wales) Act 2015:
Smarter use of resources – ensuring that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the creation of resources throughout the community that can help to deliver the Council’s well-being objectives.
3.1In accordance with the Public Sector Internal Audit Standards, the Head of Internal Audit is responsible for developing a risk-based annual audit plan which takes into account the Council's risk management framework. Within the Standards there is also a requirement for the Head of Internal Audit to review and adjust the plan, as necessary, in response to changes in the Council's business, risks, operations, programmes, systems, controls and resources. The Head of Internal Audit must also ensure that Internal Audit resources are appropriate, sufficient and effectively deployed to achieve the approved plan.
3.2The Internal Audit Plan for 2022-23 was submitted to the Governance and Audit Committee for consideration and approval on 22nd June 2022. The Plan outlined the assignments to be carried out which will provide sufficient coverage to provide an opinion at the end of 2022-23.
3.3The Plan is also flexible to allow for changing circumstances and events that may occur, such as requests to respond to new issues that may emerge.
4. Current situation/proposal
4.1Progress made against the approved Plan for the period 1st April to 8th July 2022 is attached at Appendix A. This details the status of each planned review, the audit opinion and the number of any high, medium or low priority recommendations that have been made to improve the control environment. It should be noted that some reviews listed have no audit opinion, for example advice and guidance and Governance and Audit Committee / Corporate Management Board (CMB) reporting. This is because the audit work carried out in respect of these items is planned but the nature of the work does not lead to testing and the formation of an audit opinion.
4.2Appendix A illustrates that as at the 8th July 2022, 4 audits have been completed with an opinion being provided. A further audit has also been completed, the draft report issued and feedback is awaited from the Service Department. A total of 7 audits are currently on-going and another 9 have been allocated to Auditors and are due to commence during the next few months.
4.3Based on the assessment of the strengths and weaknesses of the areas examined through testing of the effectiveness of the internal control environment an audit opinion of substantial assurance has been given to 3 completed audit reviews and an opinion of reasonable assurance to the other completed audit review.
4.4Appendix A identifies that to date 1 medium priority and 2 low priority recommendations have been made to improve the control environment. The implementation of these recommendations is being monitored to ensure that the identified and agreed improvements are being made and progress will be reported to the Committee.
5. Effect upon policy framework and procedure rules
5.1There is no effect upon the policy framework and procedure rules.
6. Equality Act 2010 implications
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Progress Against the IA Plan Appendix AAppendix | 465 KB | Download |
PDF |
Progress Against the Internal Audit Risk Based Plan 2022-23Report | 138 KB | DownloadRead as text |
Follow Governance and Audit Committee at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Sep 2023 | Approval of MinutesThe Minutes of the meeting on 26 July 2023 were approved as a true and accurate record. | Approved | Open |
| 28 Sep 2023 | Governance and Audit Committee Action RecordThe Committee noted the Action Record and provided comments, as appropriate. | Noted | Open |
| 28 Sep 2023 | Code of Corporate GovernanceGovernance and Audit Committee considered and, subject to some minor changes, approved the Council’s Code of Corporat... | Approved | Open |
| 28 Sep 2023 | Ethical Investment PolicyThe Governance and Audit Committee considered the and agreed its inclusion in future Treasury Management Strategies. | Agreed | Open |
| 28 Sep 2023 | Progress Against the Internal Audit Risk Based Plan 2023-24Members of the Committee noted the content of the report and the progress made against the 2023-24 Internal Audit Ris... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.