Resolved
That the Committee noted the progress to date to improve the DFG service and current position.
Governance and Audit Committee noted this item on Thursday 13 October 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Committee noted the progress to date to improve the DFG service and current position.
1.1The purpose of this report is to update the Governance and Audit Committee on actions taken to progress improvements to the Disabled Facilities Grant (DFG) service and provide information on the position to date.
2. Connection to corporate well-being objectives / other corporate priorities
2.1This report assists in the achievement of the following corporate well-being objectives under the Well-being of Future Generations (Wales) Act 2015:-
1. Helping people and communities to be more healthy and resilient - taking steps to reduce or prevent people from becoming vulnerable or dependent on the Council and its services. Supporting individuals and communities to build resilience, and enable them to develop solutions to have active, healthy and independent lives.
2. Smarter use of resources – ensure that all resources (financial, physical, ecological, human and technological) are used as effectively and efficiently as possible and support the creation of resources throughout the community that can help to deliver the Council’s well-being objectives.
3.1Previous reports to the Governance and Audit Committee, Cabinet and Cabinet / Corporate Management Board (CCMB) have outlined the critical need to re-shape and improve the delivery of the DFG service within Bridgend. Members of the Governance and Audit Committee received a report on 22nd April 2021 outlining the new model of service and a further report on 11th November 2021 providing an update on progress made in relation to the implementation of the new model, together with the actions taken to meet the recommendations of the Audit Wales report in 2017/18 on the Service Users Perspective. Of particular note within that report was a key recommendation regarding Council controls: ‘Council needs to be assured that it has appropriate controls in place to provide effective oversight of the adaptations process, given it is ultimately responsible for the delivery of the adaptation’.
3.2Members also received information on actions taken to respond to the Regional Internal Audit Service report in 2019/20 which had concluded that there was Limited Assurance in relation to the service. 3.3 On 1st April 2021, the Council ceased the provision of the agent delivery model and the functions for end to end delivery of DFGs and ceased providing contact details for local agents (external businesses that oversee works). However, the applicant still has the choice to go externally for DFG works to be delivered. As at this point, there were works already under the remit of various agents and a number of legacy jobs which were required to be fulfilled by agents as this work continued to be under their remit. Since then a number of cases have been returned to the Council as the agent was unable to fulfil the jobs due to the complexity. This meant that the service dealt with additional numbers of unexpected and complex cases.
3.4The report to Cabinet on 19th January 2021 outlined the potential risks with regards to the internalisation of the service and move to a new operating model which could mean that the Council is unable to achieve the aspirational targets which have been outlined in numerous reports. Risks identified at that time included the inability to recruit staff that would affect the timeline; delays in the new Framework Agreement or the ability to enter into the Collaboration Agreement with Neath Port Talbot County Borough Council (NPTCBC); and in general the availability of contractors and material costs.
3.5A number of key actions were identified to develop the new operational model and this report provides an update on the progress made on these key components of change below and responds to the risks identified above.
4. Current situation/proposal
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Disabled Facilities Grant: Progress Report And Position StatementReport | 364 KB | DownloadRead as text |
Follow Governance and Audit Committee at Bridgend and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Sep 2023 | Approval of MinutesThe Minutes of the meeting on 26 July 2023 were approved as a true and accurate record. | Approved | Open |
| 28 Sep 2023 | Governance and Audit Committee Action RecordThe Committee noted the Action Record and provided comments, as appropriate. | Noted | Open |
| 28 Sep 2023 | Code of Corporate GovernanceGovernance and Audit Committee considered and, subject to some minor changes, approved the Council’s Code of Corporat... | Approved | Open |
| 28 Sep 2023 | Ethical Investment PolicyThe Governance and Audit Committee considered the and agreed its inclusion in future Treasury Management Strategies. | Agreed | Open |
| 28 Sep 2023 | Progress Against the Internal Audit Risk Based Plan 2023-24Members of the Committee noted the content of the report and the progress made against the 2023-24 Internal Audit Ris... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.