That the Committee approved the above application, subject to the Conditions contained in the report of the Corporate Director – Communities:- Proposal: Remove Condition 19 (Construction Method Statement) of P/19/174/RLX by the provision of details. Subject to the inclusion of the following added Conditions:- 21. Notwithstanding the submitted and agreed Construction Method Statement, no further works on Phase 3 of the development shall commence until the provision of a 1m wide fully heras fenced pedestrian refuge is provided on the eastern edge of the existing access driveway. The pedestrian refuge will link the dwellings of Plots 2, 3 and 4 to the existing footway provision. The pedestrian refuge shall be implemented before any further development on Phase 3 and retained for pedestrian safety for the duration of the construction period. Reason: In the interests of highway and pedestrian safety. 22. Within two months from the date of this consent, the incomplete section of the pedestrian safety located on the eastern side of the bell mouth entrance to the site fronting Park Street, shall be completed and retained in permanent materials, to ensure a continuous pedestrian route onto Park Street, for the existing residents of the site. Reason: In the interests of highway and pedestrian safety.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
REFERENCE: P/22/85/RLX APPLICANT: Park Tree Homes Ltd c/o C2J Architects, Unit 1a Compass Business Park, Pacific Road, Cardiff, CF24 5HL LOCATION: Coed Parc Park Street Bridgend CF31 4BA PROPOSAL: Remove condition 19 (Construction Method Statement) of P/19/174/RLX by the provision of details RECEIVED: 07 March 2022 APPLICATION The Section 73 application effectively seeks to remove pre-commencement condition 19 attached to the most recent approval on this site (P/19/174/RLX) through the submission of details.
The most recent decision (P/19/174/RLX refers) itself followed an appeal decision reference P/16/610/FUL. Both decisions are attached at Appendix 1 of this report.
The application also originally sought the removal of condition 8 relating to the landscaping of the site through the submission of details but this element has been removed from the proposal to allow more time to negotiate improvements and to receive an updated tree survey and report. The landscaping condition will be reworded to seek submission of details within 3 months of the date of this consent as follows:
8. Within 3 months of the date of this consent, details of both hard and soft landscape works shall be submitted to and approved in writing by the local planning authority. These details shall include: (i) a statement setting out the design objectives and how these will be delivered; (ii) earthworks showing existing and proposed finished levels or contours; (iii) means of enclosures and retaining structures; (iv) other vehicle and pedestrian access and circulation areas; (v) hard surfacing materials; (vi) minor artefacts and structures (e.g. furniture, play equipment, refuse or other storage units, signs, etc.), (vii) details of trees to be removed and retained on site, together with details of the method of protection of the trees to be retained, and (viii) water features.
The development shall be implemented in strict accordance with the approved scheme prior to the beneficial occupation of the dwellings in Phase 3.
Reason: To maintain and improve the appearance of the area in the interests of visual amenity and to promote nature conservation.
This application seeks approval of the construction method statement (CMS). More specifically, the condition attached to P/19/174/RLX stated:
19. No development shall commence, including any works of demolition, until a Construction Method Statement has been submitted to, and approved in writing by, the Local Planning Authority. The approved statement shall be adhered to throughout the construction period. The statement shall provide for: (i) the parking of vehicles of site operatives and visitors; (ii) loading and unloading of plant and materials; (iii) storage of plant and materials used in constructing the development; (iv) the erection and maintenance of security hoarding including decorative displays and facilities for public viewing, where appropriate; (v) wheel washing facilities; (vi) measures to control the emission of dust and dirt during demolition and construction; (vii) a scheme for recycling/disposing of waste resulting from demolition and construction works and; (viii) hours restrictions for construction work.
Reason: In the interest of highway safety.
The applicant commenced development without discharging these conditions and is therefore in breach of the pre-commencement conditions.
At this point in time, Phase 1 has been completed with access from Park Street (one dwelling at the southern end of the site and 3 mid-link properties to the east of the Grade II Listed former library building) and works to weatherproof the Listed Building as part of Phase 2 of the wider development have also commenced.
The remaining phase (Phase 3) relates to 9 detached properties to the northern end of the site. These properties (and the semi-detached property to the west of the Listed Building) will eventually be accessed via Walters Road to the west of the site.
Fig. 1 – Aerial View of Site
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.