that Cabinet: approves the submission of the MIM Stage 2 application to WEPCo in respect of the Bridgend West scheme; and approves the nomination and appointment of Cllr Jon-Paul Blundell to be the BCBC Participant Representative on the SPB.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
submit the Mutual Investment Model (MIM) Stage 2 application to the Welsh Education Partnership Company (WEPco) in respect of the Bridgend West School Modernisation Programme scheme; and
nominate Cllr Jon-Paul Blundell to be the Bridgend County Borough Council (BCBC) Participant Representative on the Welsh Education Partnership Strategic Partnering Board (SPB).
Background
2.1On 14 September 2021, Cabinet approved the submission of the Bridgend West Stage 1 MIM ‘New Project Request’ to Welsh Government. The Bridgend West scheme includes provision of a new-build, two-form-entry English-medium school on the Marlas Estate (suitable for Afon y Felin and Corneli Primary Schools combined) and provision of a new-build, two form-entry Welsh-medium school on the existing Ysgol y Ferch o’r Sgêr/Cornelly Children’s Integrated Centre/Corneli Primary School site (suitable for an enlarged Ysgol y Ferch o’r Sgêr).
2.2The necessary School Organisation Code statutory processes were completed and, on 22 June 2021, Cabinet determined to proceed with the Bridgend West proposal as originally published (that is, to discontinue Corneli Primary School, Greenfield Terrace, North Cornelly, CF33 4LW and Afon Y Felin Primary School, Heol Y Parc, North Cornelly, CF33 4PA and establish a new English-medium primary community school to be maintained by Bridgend County Borough Council on land off Gibbons Way at Plas Morlais with effect from 1 September 2023 and to make a regulated alteration to Ysgol y Ferch o’r Sgêr in the form of an enlargement with effect from 2 September 2024).
2.3While drafting the ‘New Project Request’ documentation, Gleeds (the Welsh Government appointed project management company for all MIM schemes) revisited the indicative construction programme originally provided by them at the time of the local authority’s Strategic Outline Case submission to Welsh Government and the statutory consultation process under the School Organisation Code. The revised programme dates differed significantly from those originally supplied and subsequently published in the statutory notice.
2.4Given that the revised programme dates differed significantly from those originally supplied and subsequently published in the statutory notice, Cabinet determined, on 19 July 2022, to modify the planned opening date of the new Bridgend West English-medium school to September 2024 (the planned opening date may be subject to further modification as the scheme progresses).
2.5Following a series of engagement meetings with key stakeholders, WEPco developed a concept design and completed a Stage 1 report, which enabled an Outline Business Case (OBC) submission to be made to Welsh Government on 2 November 2022.
2.6The SPB acts as the primary mechanism for managing WEPCo's performance and ensuring the commitments contained in the Strategic Partnering Agreement (SPA) are adhered to. The SPB is the central forum in which the Participants work together with WEPCo, Welsh Government and stakeholder representatives. In July 2020, Cabinet determined that Cllr Dr Charles Smith (who, at that time, was the Cabinet Member with responsibility for education) would be BCBC’s representative on the SPB.
3. Current situation/proposal
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.