that Cabinet: Noted this report and the detailed work undertaken to date on this project. Agreed to pursue Option B and withdraw from the project at this stage, due to the Council’s inability to meet the significant financial commitments required and the timescales of the project. However, it is also recommended that the Council has a dialogue with partners, including Welsh Government and for them to identify an alternative route forward with MEL. Delegated authority to the Corporate Director – Communities, in consultation with the Section 151 Officer and Monitoring Officer, to give notice to MEL of the intention to withdraw from the Memorandum of Understanding dated 8th July 2022.
Word for word from the decision Bridgend published for this meeting.Source: democratic.bridgend.gov.uk
1.1The report will provide a review on the HyBont Project to date and ask Cabinet to determine the way forward. It outlines what are currently considered to be the next steps and estimated associated costs if Cabinet agree for the Council to continue in its current role in the project.
1.2This report does not include a full risk analysis, as this would require further due diligence and legal advice. Therefore, at this stage the review only relates to the financial implications of continuing with the project.
Background
2.1In 2021 Welsh Government were approached by the Japanese Consortium Marubeni, global specialist in renewables and hydrogen projects, to ask if they were interested in an investment opportunity for a Hydrogen Demonstrator Project in Wales. Welsh Government then asked BCBC if they would consider being part of the implementation of this project. The Japanese Government’s New Energy and Industrial Technology Development Organisation (NEDO) has pledged £13m to co- fund Hydrogen Power Demonstrator Projects with the Marubeni Corporation in the UK. The key to this project was the supply of Green Hydrogen power for heat and transportation using green energy sources.
2.2Whilst the project was classed as a demonstrator, it was not demonstrating the hydrogen production itself, i.e. using an electrolyser to produce hydrogen. This is not new technology and is currently being used across 16 other locations in the UK, in addition to a wide application in Europe and Worldwide. Examples of hydrogen production and uses already in existence in the UK including Aberdeen City Council and their bus fleet, Wright Bus in Northern Ireland. Also, HydroFLEX in Birmingham, which is a ground breaking partnership between the University of Birmingham and Porterbrook which is supported by a £750,000 grant from UK Government. This is to develop a hydrogen powered application to retrofit from 2023 into current in service diesel trains, to help decarbonise the rail network. With the Hybont project the demonstrator component is the software that is planned to be used. Put simply, this will work to assess demand for hydrogen and match it to the times when it is cheapest to produce, so both lowering the costs of production and reducing waste and making the process more efficient. This is what is being funded for demonstration via the proposed Hybont Project and not the production of the hydrogen or its application.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Engagement And Participation StrategyThat Cabinet gave approval for the commencement of a public consultation on the draft Engagement and Participation St...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.