Resolved
RESOLVED - That the content of the report approved by the Cabinet at its meeting held on 12 June be noted .
Audit Committee approved this item on Thursday 26 June 2008. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED - That the content of the report approved by the Cabinet at its meeting held on 12 June be noted .
CABINET / AUDIT Agenda Item 18 Brighton & Hove City Council COMMITTEE
Subject: Targeted Budget Management (TBM) Capital Outturn 2007/08 Date of Meeting: 12 June 2008 / 26 June 2008 Report of: Director of Finance & Resources Contact Officer: Name: Stuart Taylor Tel: 29-1074 E-mail: [email protected] Key Decision: Yes Forward Plan No.8 Wards Affected: All
FOR GENERAL RELEASE
1. SUMMARY AND POLICY CONTEXT: 1.1 This report sets out the capital outturn for 2007/08. 1.2 This report also highlights programme slippage, details budget changes and seeks approval for carry forwards to the 2008/09 programme.
2. RECOMMENDATIONS: (1) Approve the changes to the capital budget, as set out in Appendix 1 (2) Note the programme slipped by 3.48%, as set out in paragraph 3.3. (3) Approve the carrying forward of 2007/08 slippage (£1.407 million) into the 2008/09 capital programme, to meet on-going commitments on these schemes.
3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS: 3.1 Capital Budget 2007/08 On 7 February 2008, Policy & Resources Committee considered the month 9 capital monitoring report and agreed a revised capital budget of £44.939 million. Appendix 1 to this report shows in detail the proposed changes to that budget since month 9, resulting in a final proposed 2007/08 capital budget of £40.444 million. Chart 1 shows the resources that make up that budget.
81 Chart 1 Capital Resources £ '000 Other External Council Resources Contributions £6,867 £991
Borrowing £10,545
Grants, £22,041
3.2Capital Outturn The table below shows the capital outturn for 2007/08
Budget New Existing Budget Revised Actual Slippage Saving / month schemes schemes re-profiling budget Outturn into next (shortfall) 9 – resource year Department changes £‘000 £‘000 £‘000 £‘000 £‘000 £‘000 £‘000 £‘000 Cultural 1,298 0 (6) (104) 1,188 1,088 100 0 Services Finance & 6,190 41 10 (1,235) 5,006 4,697 309 0 Resources ASC & HRA 16,731 13 (124) (1,241) 15,379 14,599 596 184 CYPT 7,557 120 (27) (320) 7,330 7,108 165 57 Environment 9,881 75 553 (1,290) 9,219 8,982 237 0 Sub-total 41,657 249 406 (4,190) 38,122 36,474 1,407 241
Schools 3,282 0 (237) (723) 2,322 2,322 0 0 DFC
Total 44,939 249 169 (4,913) 40,444 38,796 1,407 241 3 The 2007/08 capital outturn is £38.796 million. A further £1.407 million of the budget is needed to complete these projects and is requested to be carried forward to the 2008/09 programme. Net savings have been made of £0.241 million. This relates to two areas of the programme: • Housing stock programme £0.184 million Cash incentive £0.080 million – there was no take-up of scheme in 2007/08. A further £0.080 million allocation has been made in 2008/09
82 budget, so this saving is to be returned to HRA reserves for future re- allocation. ICT fund £0.104 million - following the decision to retain the housing stock, a new ICT strategy has been in development. It has not therefore been appropriate to purchase individual solutions without fitting them into the overall strategy. This underspend will therefore be returned to HRA reserves for future re-allocation. • Children’s Centres £0.057 million Savings were identified in order to allow this ring-fenced grant to be re- allocated towards the nursery class at Moulsecoomb Primary School in 2008/09. The grant can be carried forward for use in 2008/09 without the loss of funding. 3.3 Capital Slippage The council endeavours to deliver its capital programme on time and within budget and as such monitors against a challenging target of spending at least 95% of the approved capital programme each year. The graph below shows how forecasts of slippage compare to previous years
4 % of budget
2005/06 3 2006/07 2007/08 2
0 1 2 3 4 5 6 7 8 9 10 11 12 Month
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Targeted Budget Management (TBM) Capital Outturn 2007/08Report | 184 KB | DownloadRead as text |
PDF |
View item 18. as HTML 280 KBReport | 280 KB | Download |
Follow Audit Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 24 Apr 2012 | Procedural BusinessRESOLVED - That the press and public be excluded from the meeting during consideration of Item 88 onwards. | Decided | Open |
| 24 Apr 2012 | Minutes of the Previous MeetingRESOLVED- That the minutes of the previous meeting held on 21 February 2012 be approved and signed as the correct rec... | Approved | Open |
| 24 Apr 2012 | Audit commission: progress report 2011/12RESOLVED- That the Audit Committee notes the report and progress made. | Decided | Open |
| 24 Apr 2012 | Audit commission: opinion audit plan 2011/12RESOLVED- That the Committee notes the 2011/12 audit plan for the audit of the financial statements and value for mon... | Decided | Open |
| 24 Apr 2012 | Assurances from the audit committee as the body charged with governance 2011/12RESOLVED- That the Audit Committee notes the response to the Audit Commission’s letter to those charged with governan... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.