Housing Cabinet Member Meeting, Wednesday 10 September 2008 at 4.00pm

Housing Management Lift Condition Report

Agreed Executive 2 papers

Housing Cabinet Member Meeting agreed this item on Wednesday 10 September 2008. Below is the council's own wording, with the papers it was decided on.

Item44

Resolved

1 That the recommendation to tender for a long term agreement (9 years) for the maintenance, repair and refurbishment of all HRA lifts be approved. 2 That the Director of Adult Social Care & Housing be given delegated powers to approve the award of the contract for the repair, maintenance and refurbishment of the HRA lifts, following financial due diligence and cost comparisons of the tenders offered under OJEU, following consultation with the Cabinet Member for Housing.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Housing Cabinet Member Meeting, 6 pages

Recommendations

2.1(1) That the Cabinet Member for Housing approve the recommendation to tender for a long term agreement (9 years) for the maintenance, repair and refurbishment of all HRA lifts.

2.2(2) That the Director of Adult Social Care & Housing be given delegated powers to approve the award of the contract for the repair, maintenance and refurbishment of the HRA lifts, following financial due diligence and cost comparisons of the tenders offered under OJEU, following consultation with the Cabinet Member for Housing.

3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS:

3.1The existing lift servicing and maintenance contract expired in 2005 and has been extended for the last 4 years. The council’s standing orders make it clear that this contract should be retendered and not extended beyond 31st March 2008 unless for exceptional reasons.

3.2The existing contract has increased by RPI every year and no longer represents value for money. 17 3.3 The present contract is not subject to performance and cost efficiencies and doesn’t meet the councils drive to become a three star authority, nor does it cover major repair or refurbishment. These works are presently tendered separately which increases the frustration of residents when a lift breaks down and there is a time delay as a result of the tender process.

3.4The draft timetable of events is as follows:

Event Completion date Appointment of consultants 21 July 2008 (Delegated authority) Complete condition survey 15 August 2008 Complete draft report 29 August 2008 1st stage S20 Notice 22 August 2008 PQQ 12 September 2008 ITT 27 October 2008 Tender report 20 December 2008 2nd stage S20 Notice 23 January 2009 Appoint contractor 24 January 2009 Commence on site 1 April 2009

Consultation

4.1Section 20 consultation has commenced with all affected leaseholders.

4.2A full report on the condition of the lifts will be presented to future area panels.

5. FINANCIAL & OTHER IMPLICATIONS:

Financial Implications: 5.1 The long term contract for the servicing, maintenance, repairs and refurbishment of all HRA lifts will require funding from the HRA revenue and Capital Programme.

The current existing revenue budget for lift servicing and maintenance is £90,000 per annum and there is a contingency for Lifts of £250,000 held in reserves (see HRA Capital Programme Report 2008/09 and 2009/10 approved by Policy & Resources 3 April 2008).

The HRA 30 year Business Plan includes estimated funding requirements of approximately £10.7m over the next 9 years for Lifts (shown under Health & Safety repairs).

Once the full report of the conditions of the lifts has been received the estimated costs, funding and profiling of works will be reviewed as part of the 2009/10 Revenue and Capital Programme Budget setting process 18 during October/November, with the final HRA budget report 2009/10 being reported to Housing Cabinet in February 2009.

Finance Officer Consulted:Susie Allen Date: 14/08/08

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 44 Lift report Cabinet Member Meeting V2 10-09-08Report 6 pages DownloadRead as text
PDF
View as HTML (44./2) 62 KBReport 62 KB Copy on its way

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. Housing Management Lift Condition ReportThis decision
  2. Council Housing Asset Management PlanDecided
  3. Update on Housing Management of Brickfields DevelopmentDecided
  4. Housing Management Procurement for Brickfields DevelopmentDecided
  5. Housing Supply and Asset Management PlanDecided
  6. Housing Management Decant Policy & ProposalsDecided

More from Brighton and Hove Housing Cabinet Member Meeting

All decisions
MeetingDecisionOutcome
18 Apr 2012 Procedural BusinessRESOLVED - That the press and public be not excluded from the meeting during consideration of any items on the agenda. Decided Open
18 Apr 2012 Minutes of the previous meetingRESOLVED – That the minutes of the Housing Cabinet Member Meeting held on 29 February 2012 be agreed and signed by th... Agreed Open
18 Apr 2012 Items reserved for discussionRESOLVED – That all items be reserved for discussion. Decided Open
18 Apr 2012 PetitionsRESOLVED – That the petition be noted. Noted Open
18 Apr 2012 Minutes of the Housing Management Consultative CommitteeRESOLVED – That the minutes be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies