Re-Tendering of Voluntary Sector Mental Health Provision

Approved Committee 2 papers

Joint Commissioning Board approved this item on Monday 15 September 2008. Below is the council's own wording, with the papers it was decided on.

Item20

Resolved

(1) That approval be given to holding the tendering of the services described in appendix one, pending a review of Self Directed support described in agenda item 21. The will require the Directors of the Local Authority and PCT to approve the continuation of existing contracts for a further 12 months from the 1 st April 2009. It is recommended that commissioning intentions for these WAMHS contracts be developed in line with the principles established for other care groups for Adult Social Care, and that the review work is undertaken by Adult Social Care staff, liaising as appropriate with PCT WAMHS Commissioners. (2) That approval be given to Sussex Partnership Trust (SPT) working with service users to develop a User Lead Wellness Centre at the Allen Centre. This service may be subject to the Self Directed Support agenda over time. (3) That approval be given to supporting the process of SPT reproviding Aldrington House Day Centre at the Allen Centre. SPT have already provided assurance to the Board that individual support will be provided to each service user affected. (4) That Buckingham Road Day Centre continues as it currently is provided. This service may be subject to the Self Directed Support agenda. (5) That the Preston Park Day Centre continues to be provided by the Current Provider. This service may be subject to the Self Directed Support agenda. (6) That the remodelling of accommodation services for adults with mental health problems be deferred, pending the wider accommodation services review due for report in January 2009. Brighton and Hove housing department, in collaboration with Sussex Partnership NHS Trust are progressing a comprehensive review of accommodation and Adult Social Care provision for those with mental health problems. It is recommended therefore that the following contracts are extended until March 2010 and the recommendations from this review are considered at a later date. · Brighton Housing Trust First Base Day Centre · Brighton Housing Trust Route 1 Project · Care Co-ops Floating Support · Brighton Housing Trust Sackville Gardens registered care home · Brighton Housing Trust Portland Road registered care home · Brighton Housing Trust Westbourne Gardens supported accommodation
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Joint Commissioning Board, 8 pages

THE JOINT Agenda Item 20 Brighton & Hove City Council COMMISSIONING BOARD

Subject: Re-tendering of Voluntary Sector Mental Health Provision Date of Meeting: Monday 15th September 2008 Report of: Terry Baker Contact Officer: Name: Simon Scott Tel: 545414 E-mail: [email protected] Wards Affected: All

FOR GENERAL RELEASE

1. SUMMARY AND POLICY CONTEXT:

1.1The Board is asked to consider options for managing the voluntary sector market for mental health services. 1.2 This report addresses three aspects: the conclusions of the day services review, from Board recommendations of March 2006 routine market testing services to ensure best value and the impact of Self Directed support on these contracts. 1.3 This report addresses thirteen small mental health contracts many of which will not have been market tested for 5 years by March 2009. 1.4 The Third Sector Strategy for Communities and Local Government recommends that third sector organisations be of sufficient scale and capability to develop and deliver objectives and that funders and purchasers should endeavour to join-up or standardise parts of the funding or procurement chain to minimise burdens on organisations and ensure a focus on delivery. 1.5 Local Authorities are required to extend Self Directed Support (SDS) and to implement the personalisation agenda for all care groups, and is described in the Self Directed Support Strategy later on this agenda. This is a priority LAA target and a development strongly supported by working age mental health services users in their ‘Pacing the Cage’ report to commissioners about the future of day services. 1.6 The requirement for statutory bodies to make efficiency savings in line with Gershon recommendations means that current commissioning capacity to service many small contracts is limited. Current contractors regularly express the view they would like more commissioning engagement in relation to relative small sums of money, detail of relatively minor operational issues, and advice on Organisational Development direction. 1.7 In parallel to the to the SDS agenda, consolidated third sector contracts potentially provide greater opportunities for mental health provider sustainability, improved clinical and corporate governance assurance frameworks, more efficient engagement with the statutory sector, a stronger foundation for the development of direct payments and individualised budgets, a stronger potential competitor to current providers, and more energy being spent on direct service delivery, rather than fundraising and attending meetings. 1.8 The process of consolidating third sector contracts may also result in high levels of expressed anxiety during the transition period, a short term loss of inward investment

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Re-Tendering of Voluntary Sector Mental Health ProvisionReport 8 pages DownloadRead as text
PDF
View item 20. as HTML 118 KBReport 118 KB Copy on its way

At this meeting

Whole meeting

More from Brighton and Hove Joint Commissioning Board

All decisions
MeetingDecisionOutcome
25 Mar 2013 Procedural BusinessRESOLVED - That the press and public be not excluded from the meeting. Decided Open
25 Mar 2013 Minutes of the Previous MeetingRESOLVED – That the minutes of the Joint Commissioning Board Meeting held on 28 January 2013 be agreed and signed as ... Agreed Open
25 Mar 2013 Financial Performance Report Month 10(1) That the forecast outturns for the s75 budgets as at month 10 be noted. (2) That the update on budget planning fo... Noted Open
25 Mar 2013 Sussex Integrated End of Life and Dementia Care Sussex PathwayItem deferred. Deferred Open
25 Mar 2013 Day Activities Review(1) That the progress of the and the next steps proposed be noted. (2) That it be noted that there will be a presenta... Noted Open