1 That the allocation of a further £1.01m additional funding for high quality improvements at The Lanes Car Park and minor improvements at London Road Car Park be approved. 2 That the release of £0.300 million from the Car Parks Maintenance Reserve as a contribution towards the capital costs be approved. 3 That the appointment of a works contractor by the Director of Environment be approved.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
CABINET MEETING Agenda Item 68 Brighton & Hove City Council
Subject: Refurbishment of London Road and Lanes Car Parks Date of Meeting: 18th September 2008 Report of: Director of Environment Contact Officer: Name: Austen Hunter Tel: 29-2245 E-mail: [email protected] Key Decision: Yes Forward Plan No. CAB 3315 Wards Affected: All Regency, St Peter’s & North Laine
FOR GENERAL RELEASE
1. SUMMARY AND POLICY CONTEXT:
1.1The Lanes and London Road Car Parks have been subject to minimal levels of maintenance pending a decision on the long term strategy for the city’s off- street parking. In November 2007, a basic repair and equipment update was agreed by Policy and Resources Committee together with approval to commence negotiations that would bring back in house 5 other Car Parks leased to NCP.
1.2This report provides a further update on these earlier P&R Committee agreements and requests cabinet to consider further enhancements to deliver the necessary standards that meet the Council’s business objectives and emerging financial position.
1.3Following the conclusion of lengthy negotiations, the 5 Car Parks previously leased to NCP returned to the Council on 1st September 2008. However, following a lack of investment in the remaining substantial Council run Car Parks, particularly The Lanes and London Road now require a fast-track improvement programme to bring them up, both to an appropriate standard and stem declining income levels.
1.4Additional funding and authority to appoint a works contractor is sought to carry out these improvements.
1.5These works will form part of a Citywide Parking Strategy to coordinate and raise standards at all Council operated off-street car parks.
1.6Raising the current standard in The Lanes and London Road Car Parks will improve perceptions of the City, generating additional visits and improved income.
241 2. RECOMMENDATIONS:
2.1That the Cabinet approve the allocation of a further £1.01m additional funding for high quality improvements at The Lanes Car Park and minor improvements at London Road Car Park.
2.2That the Cabinet approve the release of £0.300 million from the Car Parks Maintenance Reserve as a contribution towards the capital costs.
2.3That the Cabinet approve the appointment of a works contractor by the Director of Environment.
3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS:
3.1On 29th November 2007, Policy and Resources Committee approved an invest to save proposal of up to £1m to enhance the physical environment, increase public safety and protect income at The Lanes and London Road car parks.
3.2The £1m allocated was based upon a visual dilapidations survey intended to provide a summary overview when the Council was considering tendering out the car parks back in 2005.
3.3In 2008, following the conclusion of very complex negotiations with NCP regarding the transfer of five car parks back to the Council, the survey was updated to include provision for security and aesthetic improvements to enhance the physical environment and improve visitor perceptions within an expanding car parks portfolio. The updated survey and design specification will create a step change and transform the way the Car Parks look and feel. For many visitors the Council’s Car Parks are the ‘front door to the city’ creating first and last impressions. Emphasis is placed within the design specifications upon improved lighting, CCTV and access control technologies that will help to secure the parking areas.
3.4Tenders have been sought through the formal, European wide (OJEU) procurement process to identify a main contractor for the works. A preferred bidder will be identified in September. The works were tendered on a Design and Build basis. Tenderers have been presented with a full functional specification to achieve a high quality standard at both car parks. Required elements will be confirmed at the preferred bidder stage when it is known what, if any, additional funding is available.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.