That Cabinet recommend that Council; (1) Agree the budget for 2009/10 as shown in Appendix 1; (2) Agree the individual rent increases and decreases in line with rent restructuring principles as determined by the Government; (3) Agree the changes to fees and charges as detailed in paragraph 3.14 to 3.20; (4) Authorise the Director of Adult Social Care & Housing to implement the new rents, fees and charges, but with delegation to make any minor amendments which may appear to be appropriate in particular cases; and (5) Authorise the Director of Adult Social Care & Housing to prepare and place on deposit the statement of proposals, estimates and other particulars as required by Section 76 of the Local Government and Housing Act 1989.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
2.1That Cabinet recommend that Council; a) Agree the budget for 2009/10 as shown in Appendix 1; b) Agree the individual rent increases and decreases in line with rent restructuring principles as determined by the Government; c) Agree the changes to fees and charges as detailed in paragraph 3.14 to 3.20; d) Authorise the Director of Adult Social Care & Housing to implement the new rents, fees and charges, but with delegation to make any minor amendments which may appear to be appropriate in particular cases; and e) Authorise the Director of Adult Social Care & Housing to prepare and place on deposit the statement of proposals, estimates and other particulars as required by Section 76 of the Local Government and Housing Act 1989.
173 3. RELEVANT BACKGROUND INFORMATION
TARGETED BUDGET MANAGEMENT (TBM) 2008/09 MONTH 9 3.1 The adjusted budget for 2008/09 is a net expenditure budget of £0.250 million. The forecast outturn as at month 9 is an underspend of £0.373 million resulting in a surplus of £0.123 million, as shown in Appendix 1. The main variances are: • Salary costs are projected to underspend by £0.383 million from vacancy management pending reviews to be implemented as part of the improvement programme, together with a £0.060 million provision for the implementation of single status. • The premises repairs budgets are now projected to overspend by £0.018m and the forecast includes the following variances: o An overspend of £0.100 million (1.8% of total £5.6 million budget) for the responsive repairs contract based on an improved forecasting methodology. o The empty property repair costs overspend has increased by £0.050 million to £0.250 million due to an increase in the average cost of repair per property from £2,300 to £2,600 compared to the last year. These works are now operating through the open book process since December 2008 which enables officers to work with partners to use transparent information to achieve unit cost reductions. o An underspend on service contracts of £0.232 million due to the continuation of existing contracts, which have a lower specification than the new contracts, the costs of which have been budgeted for and which will be let in 2009/10. o An underspend of £0.100 million for cyclical decorations as more works were capitalised than anticipated. • A review by Corgi of the way that gas inspections to installation works are carried out has resulted in an efficiency saving in the use of consultants, creating an underspend of £0.140 million. • The income budget for service charges is projected to overachieve by £0.100 million in respect of leaseholder service charges due to costs for recharging being greater than anticipated at budget setting.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.