Shoreham Harbour Joint Area Action Plan

Decided Scrutiny 4 papers

Environment & Community Safety Overview & Scrutiny Committee decided this item on Monday 23 March 2009. Below is the council's own wording, with the papers it was decided on.

Item62

Resolved

RESOLVED – to arrange an additional meeting of ECSOSC to consider the JAAP; suggested dates would be circulated by the Overview and Scrutiny Support Officer.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Environment & Community Safety Overview & Scrutiny Committee

Background

2.1The regeneration of Shoreham Harbour has long been an objective of the three local authorities: Brighton & Hove City Council (BHCC); Adur District Council (ADC) and West Sussex County Council (WSCC), and the Shoreham Port Authority (SPA). Previous plans have failed to materialise for a variety of reasons, and the area, recognised as an economically under-performing area of the Sussex Coast, has continued to decline. This has taken the form of worsening indices of multiple deprivation, such as unemployment rates, educational achievement, skills and poorer health. The SPA is commercially successful and resilient, but whilst the port adds to the character of the area, unused, under-used and unsightly sites detract from the environment of the area.

2.2Meanwhile, the economy of Brighton and Hove has grown well in recent years, with local economic strengths such as the service sectors, and specialist sectors such as creative and media services leading substantial sub-regional economic growth. Current market conditions notwithstanding, this is leading to significant challenges in identifying strategic capacity for further growth in the sub-region, given the environmental constraints of the South Downs – soon to be a National Park, and the capacity of the urban fabric, as well as other capacity constraints such as transport infrastructure.

2.3For these reasons, a new approach to regeneration is being developed to provide a catalyst for change to tackle the social and environmental problems of the area and to realise the development potential of the Shoreham Harbour area for the benefit of the sub-regional economy. The regeneration programme differs from previous strategies in that:

121 • A more ambitious scale of development is proposed, to ensure that the development can generate sufficient value to support the infrastructure necessary for the programme (previous strategies made over-ambitious assumptions about infrastructure provision which did not materialise)

• A core aim of the proposals is meeting the needs of the local communities of South Portlslade, Fishersgate, Southwick and central Shoreham (previous proposals considered only the harbour area, and local communities were not sufficiently involved)

• There is a strong partnership between the three local authorities, the SPA and key government agencies (SEEDA and the HCA), committed to supporting the programme (previous partnership working was not sufficiently robust)

• Significant funding is available to the scheme though SEEDA and HCA budgets, and the governments Growth Points programme (this was not available before)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 62 JAAP progress reportReport 270 KB DownloadRead as text
PDF
Shoreham Harbour Joint Area Action PlanReport 88 KB Download
PDF
View as HTML (62./2) 232 KBReport 232 KB Download
PDF
View item 62. as HTML 70 KBReport 70 KB Download

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. Shoreham Harbour Joint Area Action PlanThis decision
  2. Adoption of the Shoreham Harbour Joint Area Action PlanDecided
  3. Proposed Submission Shoreham Harbour Joint Area Action PlanDecided
  4. Flood Risk Management Supplementary Planning Document for Shoreham HarbourAgreed
  5. Shoreham Harbour Joint Area Action PlanApproved
  6. Shoreham Harbour, Development BriefApproved

More from Brighton and Hove Environment & Community Safety Overview & Scrutiny Committee

All decisions
MeetingDecisionOutcome
7 Mar 2012 Procedural BusinessThat the press and public be not excluded from the meeting. Decided Open
7 Mar 2012 Report of the Traveller Strategy Scrutiny Panel - for agreementRESOLVED i ) that the report be endorsed ii) that the report be referred to Cabinet with the request that Cabinet ena... Noted Open
7 Mar 2012 Monitoring Scrutiny Reviews: Renewable Energy Potentialthat the actions from the scrutiny review continue to be monitored via scrutiny under the new governance arrangements. Decided Open
7 Mar 2012 Street LightingRESOLVED that a further progress report be made to Scrutiny. Decided Open
7 Mar 2012 Winter Service Plan verbal updateRESOLVED ; that if necessary a further update be made to a future scrutiny meeting. Decided Open