Resolved
(1) That the Cabinet Member agrees not to proceed with the scheme.
Environment Cabinet Member Meeting agreed this item on Thursday 25 March 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the Cabinet Member agrees not to proceed with the scheme.
2.1That the Cabinet Member decides whether or not to proceed with the scheme based on the information in this report.
3. RELEVANT BACKGROUND INFORMATION
Policy Context and history
3.1The proposal for cycle improvements along Old Shoreham Road was adopted as part of a package of capital schemes in the current Local Transport Plan 2006/07-2010/11. The scheme was intended to increase cycling trips by 5% per year, reduce congestion by 5% and improve health.
77 3.2 Officers began to develop the concept of the scheme in early 2009. Approval was granted at the Environment Cabinet Member Meeting in July 2009 to begin further work to develop the scheme and undertake a public consultation exercise.
Initial aims of the scheme
3.3The full proposed cycle route extended from Applesham Way (Portslade) to BHASVIC (Dyke Road, Hove),
3.4This scheme was proposed to be developed in two phases
§ Phase 1: BHASVIC (junction of Dyke Road and Old Shoreham Road) to Nevill Road § Phase 2: Nevill Road to Applesham Way (Portslade)
3.5The scheme was intended to provide a continuous cycle route along the entire route.
Design Issues
3.6As part of the feasibility work various options were explored including the option of locating the cycle lane on the footway. However, Old Shoreham Road is lined with a number of trees, side roads on the southern side, driveways, and in parts a narrow width of pavement, which meant this option was ruled out.
3.7Officers began work to develop a scheme on the carriageway which would consist of cycle lanes with new coloured surfacing on the existing road in each direction. The cycle scheme would also include new signs and Advanced Stop Lines as used throughout the City to improve safety at junctions.
3.8However, the opportunity to provide a continuous cycle route scheme along Old Shoreham Road is precluded by the varying road widths, substandard junctions and potential influence on road traffic flows and capacity. This is particularly notable along the Phase 2 section, but also at the junction of Dyke Road with Old Shoreham Road, and at the railway bridge.
3.9One solution for the railway bridge would be to provide an advisory cycle lane at this section however this would still mean the route could not be considered continuous. The alternative solution to an advisory lane to ensure a continuous cycle route would be to undertake some heavy and major civil engineering works involving the widening of the bridge. This would be extremely costly. A number of junctions along the route would also require major reconfiguration to accommodate cyclists safely.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Item 106 Appendix 1Appendix | 2.2 MB | Download |
PDF |
Item 106 Appendix 2Appendix | 142 KB | Download |
PDF |
Item 106 Appendix 3Appendix | 291 KB | Download |
PDF |
Old Shoreham Road Cycle RouteReport | 89 KB | DownloadRead as text |
PDF |
View as HTML (106./3) 388 KBAppendix | 388 KB | Download |
PDF |
View item 106. as HTML 104 KBReport | 104 KB | Download |
Follow Environment Cabinet Member Meeting at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 May 2011 | Procedural BusinessRESOLVED - That the press and public be not excluded from the meeting. | Decided | Open |
| 26 May 2011 | Minutes of the previous meetingRESOLVED – That, having been signed by the previous Cabinet Member as a correct record, the minutes of the meeting he... | Noted | Open |
| 26 May 2011 | Items reserved for discussionRESOLVED – That all items be reserved for discussion. | Decided | Open |
| 26 May 2011 | PetitionsRESOLVED – That the petition be noted and the following written response from Councillor Davey be provided: “Thank yo... | Noted | Open |
| 26 May 2011 | Petitions debated at CouncilRESOLVED – That the petition be noted. 6B Royal Sussex County Hospital parking 6b.1 Councillor Davey considered a pet... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.