(1) That Cabinet notes the project progress described in sections 3 and 7 of this report made since Cabinet approved landowner consent for the project to continue in December 2008. (2) That Cabinet resolve to exercise the City Council’s powers of appropriation under section 122 of the Local Government Act 1972 so that the land at the Open Market redevelopment site as identified on the plan at Appendix 1 is appropriated for planning purposes. (1) That the consideration of the item be deferred to a Special Meeting of the Cabinet to be arranged as soon as possible so as not to prejudice the council’s ability to conclude agreements before 15 March 2011.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
2.1That Cabinet notes the project progress described in sections 3 and 7 of this report made since Cabinet approved landowner consent for the project to continue in December 2008.
2.2That Cabinet resolve to exercise the City Council’s powers of appropriation under section 122 of the Local Government Act 1972 so that the land at the Open Market redevelopment site as identified on the plan at Appendix 1 is appropriated for planning purposes.
1 3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS:
3.1The council agreed to support the work of the Open Market Traders Association (“the Association”) in April 2006. At that point, the aims of the proposal were to provide a new covered market on the site of the existing Open Market, maintain rents at a similar level and provide a temporary market during redevelopment.
3.2The Association and its advisers invited Hyde Housing to join the project as development partner and since that time, Hyde has worked to bring forward a viable scheme that delivers a new market. Partnership working has progressed the scheme through an iterative process where the Association and Hyde have submitted to the council a proposal in three stages. Each staged submission has been assessed by the council’s project officer team and considered by the council’s Open Market Project Board (first meeting January 2007), where Hyde and the Association have attended to present the scheme. Project Board recommendations at each stage have then been presented to Members at Committee and more recently Cabinet for approval to continue council support for the project.
3.3Cabinet confirmed its support for the project by granting landowner consent for the outline proposal in December 2008.
3.4Hyde and the Association submitted a redevelopment proposal to RIBA Stage D in September 2009, which was given landowner consent under delegated authority in February 2010. This proposal continues to fulfil the original project aims.
3.5In accordance with December 2008 Cabinet approval, a Community Interest Company (CIC) is being formed to take ownership of the new market and be responsible for all aspects of its operation, management and maintenance. The CIC Members will be the council, the market traders, the Hyde Group and the Ethical Property Company (EPC). The latter will take a long-term lease on the workshops.
3.6Following the completion of the pre-application discussions with the Planning Team, Hyde submitted a planning application in December 2010.
Consultation
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.