(1) That Cabinet notes the need to urgently relocate the Print & Sign Unit (PSU) for health and safety reasons. (2) That Cabinet agrees to relocate the existing PSU to suitable alternative premises. (3) That Cabinet agrees to include the scheme to refurbish premises if necessary and relocate the PSU within the capital programme at an estimated cost of £180k to be financed through council borrowing. (4) That Cabinet delegates authority to the Strategic Director, Resources, the Head of Communications and the Head of Property and Design to implement the PSU relocation within the cost parameters agreed at 2.3 above and to the Head of Legal and Democratic Services to execute the necessary legal documentation.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
2.1That Cabinet notes the need to urgently relocate the Print & Sign Unit (PSU) for health and safety reasons.
2.2That Cabinet agrees to relocate the existing PSU to suitable alternative premises.
2.3That Cabinet agrees to include the scheme to refurbish premises if necessary and relocate the PSU within the capital programme at an estimated cost of £180k to be financed through council borrowing.
2.4That Cabinet delegates authority to the Strategic Director, Resources, the Head of Communications and the Head of Property and Design to implement the PSU relocation within the cost parameters agreed at 2.3 above and to the Head of Legal and Democratic Services to execute the necessary legal documentation.
3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS:
3.1The council’s Print & Sign Unit (PSU) is currently located at Hollingdean Depot. In 2009 a survey of all the buildings at the Depot highlighted certain deficiencies in relation to the Workplace (Health, Safety and Welfare) Regulations 1992. The building has been temporarily propped to mitigate risk, but the service requires relocation.
1 3.2 In accordance with policy, relocation of the PSU to existing Brighton & Hove City Council property was considered. New England House (NEH) was identified as a possible option. However, surveys indicated that to reduce machine noise and vibration to acceptable levels would require substantial concrete slabs to be laid. These slabs would exceed the floor loading and therefore the option of moving the existing PSU to NEH was ruled out.
3.3Suitable alternative premises were identified on the Freshfields Industrial Estate as a viable and cost effective option for the current and future expanded service.
3.4Twenty other properties were considered as being potentially viable but only Freshfields had sufficient and appropriate space to accommodate the whole of the current PSU service. The refurbishment costs of Freshfields would be at worst £180k and take approximately four (4) months to achieve.
3.5Since being notified of an alternative bid on Freshfields, Property & Design have identified four alternative sites, which the PSU are now evaluating. All will need structural surveys and assessment for viability.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.