The Level Redevelopment Contract Procurement

Approved Executive 2 papers

Environment, Transport & Sustainability Cabinet Members Meeting approved this item on Tuesday 27 March 2012. Below is the council's own wording, with the papers it was decided on.

Item100

Resolved

That the Cabinet Member for Environment approves the tender of the contract for the construction works on The Level and gives delegated authority to the Strategic Director, Place in consultation with Director of Finance to award the contract.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Environment, Transport & Sustainability Cabinet Members Meeting

Recommendations

2.1That the Cabinet Member for Environment approves the tender of the contract for the construction works on The Level and gives delegated authority to the Strategic Director for Place in consultation with the Director of Finance to award the contract.

3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS: 3.1 In July 2009 the Cabinet Member for Environment endorsed the preparation of a Parks for People funding bid. The final Masterplan and the application was endorsed by the Cabinet Member for Environment & Sustainability in July 2011. The bid was submitted in August 2011, and in December 2011 the announcement was made that our application was successful.

3.2Work has now commenced on delivering the project. Provision of Lead Landscape Architect Consultancy Services for the project has been secured through an earlier procurement process. This report seeks approval to procure a contract to carry out the construction works as part of the restoration project. The contract includes: • Demolition and removal of old buildings and structures; • Restoration of the Pavilions, Columns, Pergolas and Bridges; • Restoration of the full footprint of the old boating pond to create a new water fountain feature; • Restoration of the South Enhance including the Dolphin Lamps;

27 • Refurbishment of perimeter stone walls; • Replacement of the Rose Walk beds and hedges around the south perimeter ; • New planting of trees and floral beds; • New Pétanque Activity area • New paving throughout the site (but not including the outer perimeter paths); • New lighting, signage, fencing, gates and park furniture; and • New building housing café, public toilets and park staff facilities.

3.3The procurement activity described within this report is termed as a works contract with an anticipated value which falls under the EU threshold of £4,348,350. To prepare for the procurement process a cross departmental working group will be established to work on the specification, evaluation criteria and procurement process to ensure compliance with the Council’s contract standing orders.

3.4Due to the restricted size of the restoration project site and the interlinking nature and complexity of the elements within this construction project, it is the Council’s intention to seek one main contractor to deliver this contract.

3.5The indicative timetable for the procurement and the implementation of the contract is shown below. The contract would therefore be in place by October 2012:

Task Timescale Place advert April 2012 PQQ response period April 2012 PQQ evaluation May 2012 ITT issued End June 2012 Tender period July 2012 Tender evaluation August 2012 Agree preferred bidder August 2012 Approval report agreed September 2012 Standstill period September 2012 Contract award notice & Mobilisation September 2012 Contract start October 2012

4. COMMUNITY ENGAGEMENT AND CONSULTATION

4.1The Level bid has been subject to extensive consultation and engagement which has informed the Masterplan. This contract is key to delivering the Masterplan.

5. FINANCIAL & OTHER IMPLICATIONS:

Financial implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
The Level Redevelopment Contract ProcurementReport 82 KB DownloadRead as text
PDF
View item 100. as HTML 82 KBReport 82 KB Download

More from Brighton and Hove Environment, Transport & Sustainability Cabinet Members Meeting

All decisions
MeetingDecisionOutcome
4 May 2012 Procedural BusinessRESOLVED - That the press and public not be excluded from the meeting. Decided Open
4 May 2012 Items reserved for discussionRESOLVED – That all items be reserved for discussion. Decided Open
4 May 2012 Preston Park Traffic Regulation Order Consultation2.1 That, having taken account of all duly made representations and objections, the Cabinet Member approves as advert... Approved Open
4 May 2012 Brighton & Hove 20mph City2.1 That the Cabinet Member for Transport & Public Realm agrees the principles of the proposed outline implementation... Agreed Open
4 May 2012 Local Sustainable Transport Fund - Upgrade of the Real Time Passenger Information (RTPI) System2.1 That the Cabinet Member for Transport & Public Realm supports the upgrade of the RTPI system to GPRS and grants p... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies