Contractual Arrangements for Strengthening the King's Road Arches
AgreedCommittee2 papers
Policy & Resources Committee (pre 2015) agreed this item on Thursday 24 January 2013. Below is the council's own wording, with the papers it was decided on.
That the urgency and essential nature of the initial strengthening works to the seafront Arches and the additional, associated opportunities and benefits that these works present regarding the delivery of the i360 viewing tower be recognised; 2. That the award of the scheme contract for the urgent and essential strengthening works to the seafront arch structures between Alfresco’s Restaurant and the West Pier (referred to as Arch Numbers 36-61), under the ‘Coast Protection and Highway Structures Maintenance Framework Agreement 2012 – 2015’ be approved; and 3. That it be agreed that priority should be given to identifying and allocating funding from within the council’s budgets to enable the planned strengthening works and internal refurbishment to be undertaken during 2012/13 to 2014/15, to coincide with the planned construction programme for the i360 viewing tower.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
2.1That the Committee recognises the urgency and essential nature of the initial strengthening works to the seafront Arches and the additional, associated opportunities and benefits that these works present regarding the delivery of the i360 viewing tower.
2.2That the Committee is requested to formally approve the award of the scheme contract for the urgent and essential strengthening works to the seafront arch structures between Alfresco’s Restaurant and the West Pier (referred to as Arch Numbers 36-61), under the ‘Coast Protection and Highway Structures Maintenance Framework Agreement 2012 – 2015’.
2.3That the Committee agrees that priority should be given to identifying and allocating funding from within the council’s budgets to enable the planned strengthening works and internal refurbishment to be undertaken during 2012/13
479 to 2014/15, to coincide with the planned construction programme for the i360 viewing tower.
3. RELEVANT BACKGROUND INFORMATION/CHRONOLOGY OF KEY EVENTS:
3.1Parts of the city’s seafront consist of approximately 375 different structures, with a plan area of approximately 21,000 sq/m; and an asset value of approximately £300 million plus. The vast majority of these structures are over 120 years old and large sections of these are at the end of their serviceable life. The city’s engineers undertake regular inspections, assessments and maintenance works to keep the public safe. As part of these ongoing works, there is a management plan and outline, planned reconstruction programme for all the deficient and end of serviceable life structures. The management plan will be the subject of a future committee report.
3.2The reconstruction, strengthening and refurbishment of Kings Road Arches (numbers 36-61) between Alfresco’s Restaurant and the West Pier form part of this overall programme. Following recent surveys these arches have been found to be structurally defective. Under the Highways Act, the council has a duty to ensure that highways are adequately maintained, and as part of this it must ensure that supporting structures are safe for use and fit for purpose. It has therefore been necessary to close off a short section of the upper promenade to protect the public from any harm or danger and allow essential, initial works to begin to protect and stabilise this area. This strengthening work will involve the demolition and replacement of the deficient structures with new units that are adequate to carry certain loads (up to 40 tonnes) that may be applied to them.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy & Resources Committee (pre 2015) at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
Senior Management Team Re-OrganisationRESOLVED – That the Committee: 1) Notes the proposed officer re-organisation as set out in the report; 2) Notes that ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.