Planned Maintenance Budget Allocation 2014-15 and Programme of Works for the Council’s Operational Buildings
ApprovedCommittee6 papers
Policy & Resources Committee (pre 2015) approved this item on Thursday 20 March 2014. Below is the council's own wording, with the papers it was decided on.
(1) That the annual programme of planned maintenance works to the council’s operational buildings at an estimated cost of £3,827,880, as detailed in Appendices 2 and 3 of the report be approved; and (2) That the Executive Director Finance & Resources be granted delegated authority o enter into contracts within this budget, as required, and in accordance with Contract Standing Orders.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
Property Type Examples of works and Budget Client Officer properties covered Allocation £ Corporate - Clearance of roofs, gutters, All 96,500 Building testing, surveys & structural inspections Corporate - Water Management, Mechanical, All 825,930 Mechanical and Electrical & Lift statutory Electrical compliance & servicing contracts Historic Royal Pavilion (including Tim Thearle 623,000 £187,000 annual financing costs for stonework project), Preston Manor, Museums, West Blatchington Windmill Dome General maintenance Dome 190,000
Follow Policy & Resources Committee (pre 2015) at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
Senior Management Team Re-OrganisationRESOLVED – That the Committee: 1) Notes the proposed officer re-organisation as set out in the report; 2) Notes that ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.