Resolved
That the recommended remaining allocations of AMF bids totalling £0.275 million as detailed in paragraph 3.4 of the report be agreed.
Policy & Resources Committee (pre 2015) agreed this item on Thursday 1 May 2014. Below is the council's own wording, with the papers it was decided on.
Resolved
That the recommended remaining allocations of AMF bids totalling £0.275 million as detailed in paragraph 3.4 of the report be agreed.
2.1That Policy & Resources Committee approve the recommended remaining allocations of AMF bids totalling £0.275 million as detailed in paragraph 3.4 of this report.
3. CONTEXT/ BACKGROUND INFORMATION
3.1The Asset Management Fund (AMF) 2014/15 is a capital fund to support property improvements, property related Health & Safety requirements and access improvements under the Equality Act 2010. It forms part of the Capital Strategy 2014/15 along with the Strategic Investment Fund (SIF) of £0.25 million and the ICT Strategy Fund of £2.0 million. The AMF 2014/15 consists of a budget of £1.0 million funded from capital receipts.
3.2The AMF is managed and administered by Property & Design and relates to property related works or improvements to council properties that address three key areas:
1) General property improvements (not covered by the planned maintenance budget and other funding streams.) 2) Property related provisions under the Equality Act 2010 3) Property related Health & Safety legislation
3.3Bids are normally sought annually from client departments/delivery/support units, and are then evaluated and recommendations made for the implementation of the successful bids. However, £0.725 million of the 2014/15 AMF allocation was approved by a Special Policy & Resources Committee of the 13th September 2013, to part fund the Workstyles Phase 3 project, which includes refurbishment works at Portslade Town Hall, Hove Town Hall and Montague House
3.4The proposed overall 2014/15 AMF allocation is as follows:
Description Cost £m 1. Major Property Improvements Workstyles Phase 3: Portslade Town Hall, Hove Town 0.725 Hall and Montague House (agreed P&R 13th September 2013)
2. Equality Act Improvements Rolling programme of access improvements to corporate 0.100 buildings
3. Property Related Health & Safety Legislation Asbestos Management 0.050 Legionella Management 0.080 Fire Risk Assessment Works 0.045 TOTAL 1.000
3.5Details of the individual recommendations are listed in Appendix 2
4. ANALYSIS & CONSIDERATION OF ANY ALTERNATIVE OPTIONS
4.1Failure to improve the council’s core office accommodation, address property related access obligations under the Equalities Act 2010 and property related Health & Safety legislation would increase council risks and liabilities, inhibit service delivery, may lead to a negative perception of the council, reduce the value of our assets and prevent fulfilling the council’s priorities, aims and objectives as stated in the Corporate Property Strategy and Asset Management Plan.
5. COMMUNITY ENGAGEMENT & CONSULTATION
5.1The Workstyles project involves extensive staff consultations on customer and service delivery requirements, different ways of working, office layouts and designs.
6. CONCLUSION
6.1This report seeks to approve the remaining balance of the AMF financial allocation and the recommended bids as detailed at paragraph 3.4 and Appendix 1 for property improvements, access requirements under the Equality Act 2010 and property related Health & Safety requirements for 2014-2015
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Asset Management Fund 2014/15Report | 94 KB | DownloadRead as text |
PDF |
View item 170. as HTML 105 KBReport | 105 KB | Download |
Follow Policy & Resources Committee (pre 2015) at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 Apr 2016 | Procedural BusinessThat the press and public be excluded from the meeting during consideration of the items contained in part two of the... | Decided | Open |
| 28 Apr 2016 | Tower House1) That the Committee should read and consider the consultation outcome and the equalities impact assessment to infor... | Decided | Open |
| 28 Apr 2016 | Learning Disabilities Accommodation Services1) That the Policy & Resources Committee members should read and consider the full consultation outcome and equalitie... | Decided | Open |
| 28 Apr 2016 | Orbis Programme UpdateRESOLVED – That the Committee: 1) Notes the progress made in carrying out due diligence for Brighton & Hove City Coun... | Agreed | Open |
| 28 Apr 2016 | Senior Management Team Re-OrganisationRESOLVED – That the Committee: 1) Notes the proposed officer re-organisation as set out in the report; 2) Notes that ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.