Brooke Mead Extra Care Housing – Development Update
AgreedCommittee2 papers
Policy & Resources Committee (pre 2015) agreed this item on Thursday 12 February 2015. Below is the council's own wording, with the papers it was decided on.
That the Committee agrees an increase in the capital programme budget for the delivery of Brooke Mead extra care housing scheme to a maximum amount of £ 12m financed through unsupported borrowing in the Housing Revenue Account ( HRA ), Homes & Community Agency (HCA) Grant and a contribution from Adult Social Care, to enable the scheme to start on site before the end of March 2015. That Committee agrees to appropriate the land at Brooke Mead, Albion Street, Brighton, for planning purposes.
Word for word from the decision Brighton and Hove published for this meeting.Source: democracy.brighton-hove.gov.uk
2.1That the Committee agrees an increase in the capital programme budget for the delivery of Brooke Mead extra care housing scheme to a maximum amount of £12m financed through unsupported borrowing in the Housing Revenue Account (HRA), Homes & Community Agency (HCA) Grant and a contribution from Adult Social Care, to enable the scheme to start on site before the end of March 2015.
2.2That Committee agrees to appropriate the land at Brooke Mead, Albion Street, Brighton, for planning purposes.
3. CONTEXT/ BACKGROUND INFORMATION
3.1On 5 December 2013, Policy & Resources Committee approved a capital programme budget up to a maximum of £8.3 m for the delivery of the Brooke Mead extra care housing scheme. It also granted delegated authority to the Executive Director Environment Development & Housing (in consultation with the Executive Director of Finance & Resources) to:
59 (i) enter into a Care & Support Specialist Housing Fund (2013-18) Funding Agreement with the HCA. (ii) enter into the necessary contract (including with a development partner as necessary) to secure:
• the demolition of the existing building; • the design and build operations required to complete the development of the Brooke Mead extra care housing scheme; and • the housing management operation, in respect of the new extra care scheme.
3.2Brooke Mead is a council-led extra care housing development comprising of 45 one bedroom units of accommodation with both communal and community facilities on the ground floor. The scheme was granted planning permission on 11 December 2013. Since then, there has been considerable progress in relation to key stages of the project (see Fig 1).
Committee • P&R Committee approval 5 December 2013 consent • Planning permission granted 11 December 2013 Dec 2013
• Willmott Dixon appointed in April 2014 to manage Procurement Brooke Mead development through SCAPE Jan-Apr 2014 Framework
Pre-construction • Project Order entered into with Willmott Dixon agreement detailing programme,costs and scope of works May-Sept 2014
Detailed design • Lee Evans Partnership (architects appointed) RIBA Stage E • Design amended in response to M&E requirements and value engineering exercise Oct-Feb 2014
Sign off & project • Pre-commencement planning conditions start • Site preparation for demolition Mar 2014 Fig 1 – Pre-construction phase of Scape
3.3In April 2014, the council appointed Willmott Dixon contractors to manage the Brooke Mead development through a procurement framework known as SCAPE. The framework comprises five key stages: inception, feasibility, pre- construction, construction and post construction. In support of the pre- construction phase, Willmott Dixon carried out a build cost review in June 2014 based on the initial design stage. This cost review demonstrated that the total scheme costs had increased by £1.5m to £9.8m. The increase in build costs stems from the high number of site abnormals such as ground
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Policy & Resources Committee (pre 2015) at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
Senior Management Team Re-OrganisationRESOLVED – That the Committee: 1) Notes the proposed officer re-organisation as set out in the report; 2) Notes that ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.