Housing Committee (pre 2015), Wednesday 4 March 2015 at 4.00pm

Pilot of Level Access Shower Installations: Update

Noted Committee 2 papers

Housing Committee (pre 2015) noted this item on Wednesday 4 March 2015. Below is the council's own wording, with the papers it was decided on.

Item76

Resolved

(1) That the positive impact this pilot has had, in terms of increasing the number of accessible council owned properties for people in housing need in Brighton & Hove is noted. (2) That the work to proactively deliver the installation of level access showers by identifying suitable one bedroom ground floor properties when they become empty, be continued.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Housing Committee (pre 2015)

Recommendation

2.1To note the positive impact this pilot has had, in terms of increasing the number of accessible council owned properties for people in housing need in Brighton & Hove.

2.2To continue to proactively deliver the installation of level access showers by identifying suitable one bedroom ground floor properties when they become empty.

3. CONTEXT/ BACKGROUND INFORMATION

3.1This pilot was introduced as part of the review of the Brighton & Hove (Property) Standard, with the aim of increasing the number of properties within the council owned housing stock that are suitable for people with mobility difficulties.

3.2On 10 September 2014 a recommendation was approved by Housing Committee to introduce an Adaptations Policy for council owned and managed properties. It is appropriate to consider including this area of work within that policy.

87 4. RESULTS OF PILOT

4.1The table below provides information for all nine properties identified as suitable for the installation of level access showers to date. Three of these properties have been successfully re-let to tenants with accessibility requirements, four have become empty recently and empty property works are underway and one is advertised in Homemove for re-letting (at time of writing this report 16 Feb 2015).

Ward Total Number of Time on General Cost of calendar days Homemove waiting list repair adaptatio empty bids of person cost to ns to re-housed re- property let(excl. shower)

Moulsecoomb & 45 days 65 bids Band C £986 £3540 Bevendean May 2010 Moulsecoomb & 21 days 97 bids Band B £1600 £3623 Bevendean August 2012 Queens Park 10 days 198 bids Band A £1411 £3322 May 2014 North Portslade Empty Empty homes work underway

East Brighton Empty Currently advertised in Homemove

Hangleton & Knoll Empty Empty homes work underway

Goldsmid Empty Empty homes work underway

Hollingdean & Empty Empty homes work underway Stanmer

4.2It was anticipated that up to 15 properties a year would become available and be suitable for this work. There were a total of 81 one bedroom ground floor flats that were re-let during the period of this pilot. Of these, eight properties were actually suitable for the installation of a level access shower and categorisation as a Mobility 3 rated property. There are a number of factors that affect the mobility rating of a property including the property itself, the location of the property and local amenities and transport links. In order to adequately support tenants with a disability, level access showers were only installed in properties that would be suitable for a disabled tenant.

4.3It was anticipated there would be no increase in the general repair costs to empty properties, and acknowledged that installing a level access shower would be more expensive than simply replacing a bath or carrying out repair work. However in many cases new tenants move into properties without adaptations and subsequently contact the council through Access Point and request adaptations such as level access showers. Details of the cost of installing level access showers in each of the eight properties is included in the table at 4.1.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Pilot of Level Access Shower Installations: UpdateReport 79 KB DownloadRead as text
PDF
View item 76. as HTML 100 KBReport 100 KB Download

At this meeting

Whole meeting

More from Brighton and Hove Housing Committee (pre 2015)

All decisions
MeetingDecisionOutcome
4 Mar 2015 Procedural BusinessRESOLVED - That the press and public not be excluded from the meeting. Decided Open
4 Mar 2015 Call OverIt was agreed that all items be reserved for discussion. Agreed Open
4 Mar 2015 Public InvolvementRESOLVED- That the Public question be noted. 69.7 There were no deputations. Noted Open
4 Mar 2015 Housing Adaptations and Investment update(1) That the capital expenditure to date and commitments going forward, the action taken to mitigate pressures this y... Noted Open