Item50
Resolved
That the Committee: 1) Agree to the two stage phased approach to the introduction of charges for pre-application advice as set out in paragraphs 3.11 and 3.12. 2) Grants delegated authority to the Executive Director Environment, Development & Housing to negotiate the terms of bespoke, cost neutral PPAs on major development schemes as part of a pre-application advice service. 3) Grants delegated authority to the Executive Director Environment, Development & Housing to proceed with the procurement and subsequent award of a contract to provide cost neutral, multidisciplinary expert design review advice to the LPA.
Word for word from the decision Brighton and Hove published for this meeting.