Resolved
View the decision text for item 61.
Housing & New Homes Committee decided this item on Wednesday 13 January 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 61.
That the Audit & Standards Committee:
2.1Note that the council’s housing revenue account was over-charged by an amount estimated by audit at more than £300,000 over a 17 month period for work carried out by a sub-contractor working on the housing repairs and improvements contract. 2.2 Note that the council expects to recover the overpayments from the main contractor, Mears Ltd. 2.3 Note that the council is working positively with Mears Ltd to identify any other overpayments that may have been made and to prevent any overpayments in the future.
3. CONTEXT/ BACKGROUND INFORMATION
3.1Mears Ltd provides a comprehensive responsive repairs, planned maintenance and major works service for council homes across the city under a 10-year contract. Around 20% of the annual contract is responsive repairs of which just under 30% (by number of jobs) is carried out by sub-contractors. In terms of value, the contract is expected to cost £27m in 2015/16. Approximately 4% of the annual cost relates to sub-contracted responsive repairs. Sub-contractors are also used extensively for planned and major works but these are subject to different payment, audit and sign off regimes.
135 3.2 Mears Ltd has contractual responsibility for undertaking post inspections of 10% of all completed works and the council’s housing contract compliance team also carry out checks. Following an audit of housing repairs in 2013/14, the Housing Contract Compliance Team enhanced its assurance processes by increasing the number of physical post-inspections (with effect from February 2015). In May 2015 these inspections identified a potential over-charging issue by a sub- contractor. After initial investigation, the Housing Contract Compliance Team contacted Internal Audit with their concerns.
3.3Internal audit, working jointly with quantity surveyors from the council’s Housing team, inspected 46 repairs completed by a single sub-contractor to identify the extent of any potential overcharging and to identify shortfalls in internal controls.
3.4Further inspections were then carried out by Mears Ltd and council surveyors.
4. ANALYSIS & CONSIDERATION OF ANY ALTERNATIVE OPTIONS
4.1The audit concluded that mechanisms put in place by Mears Ltd to identify overcharging were not operating as intended. There was significant evidence that a particular subcontractor had routinely overcharged Mears Ltd and that these costs had been passed onto the council. The audit concluded that the housing revenue account had been overcharged and estimated that the overcharge was in excess of £300,000 for the 17 month period examined.
4.2The contractual mechanism allows for review of valuations after submission. This takes place on a monthly basis as a matter of course. In this case, however, the overcharging was not identified at the time and so would need to be addressed by correcting historical valuations.
4.3The audit made a series of high priority recommendations to:
stop the sub-contractor from working on council contracts;
identify and recover all overpayments made by the council to Mears Ltd;
improve controls by Mears Ltd over the work carried out by sub-contractors;
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Overpayments on the housing repairs and improvement contractReport | 287 KB | DownloadRead as text |
PDF |
Overpayments on the housing repairs and improvement contractReport | 91 KB | Download |
PDF |
View as HTML (61./2) 34 KBReport | 34 KB | Download |
PDF |
View item 61. as HTML 30 KBReport | 30 KB | Download |
Follow Housing & New Homes Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2024 | Moulsecoomb Hub and Housing ProjectView the decision text for item 61. | Decided | Open |
| 13 Mar 2024 | Private Sector Housing: Discretionary Additional Licensing SchemeView the decision text for item 62. | Decided | Open |
| 13 Mar 2024 | Private Sector Housing: Discretionary Selective Licensing SchemeView the decision text for item 63. | Decided | Open |
| 13 Mar 2024 | Draft Housing Strategy 2024 to 2029View the decision text for item 64. | Decided | Open |
| 13 Mar 2024 | Housing, Health & Safety Update ReportView the decision text for item 65. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.