Resolved
View the decision text for item 67.
Audit & Standards Committee decided this item on Tuesday 10 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 67.
Appendix 1
Summary of action taken in the period April to September 2016
Treasury Management Strategy
New long term borrowing £19.322 of new debt was undertaken during the first 6 months.
Debt maturity £3.424m of long-term borrowing was repaid in the first 6 months.
Lender options where the lender has the exclusive option to request an increase in the loan interest rate and the council has the right to reject the higher rate and repay instead (LOBO), on 4 loans were due in the 6 month period but no option was exercised.
Three of the council’s LOBO loans were converted to fixed rate loans during the period by the lender.
Debt restructuring Opportunities to restructure the debt portfolio are severely restricted under changes introduced by the Public Works Loan Board in October 2007. No restructuring was undertaken in the first 6 months.
Weighted average maturity profile The weighted average maturity period of the portfolio has increased slightly from 29.5 years to 30.2 years as a result of the changes in the debt portfolio over the last 6 months.
Capital financing requirement The prudential code introduces a number of indicators that compare borrowing with the capital financing requirement (CFR) – the CFR being amount of capital investment met from borrowing that is outstanding. Table 1 compares the CFR with actual borrowing.
Table 1 – Capital financing requirement compared to debt outstanding 1 April 2016 30 Sept 2016 Movement in period Capital financing £346.7m requirement (CFR) Less PFI element (£53.9m) (*) Net CFR £292.8m £310.5m £17.7m Long-term debt £245.1m (**)£261.0m £15.9m O/s debt to CFR (%) 83.7% 84.1% 0.4% (*) projected 31 March 2017 (**) As at 30 Sept 2016
Traditionally, the level of borrowing outstanding is at or near the maximum permitted in order to reduce the risk that demand for capital investment (and hence resources) falls in years when long-term interest rates are high (i.e. interest rate risk). However given the continued volatility and uncertainty within the financial markets, the council has maintained the strategy of keeping borrowing at much lower levels (as investments are used to repay debt). Currently outstanding debt represents 84.1% of the projected
211 capital financing requirement.
Cash flow debt / investments The TMPS states that “The council will maintain an investment portfolio that is consistent with its long term funding requirements, spending plans and cash flow movements.”
An analysis of the cash flows reveals a net surplus for the first 6 months of £7.2m. The surplus has been used to increase investments (Table 2).
Table 2 – Cash flow April to September 2016 Payments Receipts Net cash Total for period £457.8m £465.0m +£7.2m Represented by:
Increase in long term borrowing -£15.9m Increase in investments +£23.5m Decrease in balance at bank -£0.4m +£7.2m
Prudential indicators Budget Council approved a series of prudential indicators for 2016/17 at its meeting on 25 February 2016. Taken together, the indicators demonstrate that the council’s capital investment plans are affordable, prudent and sustainable.
In terms of treasury management the main indicators are the ‘authorised limit’ and ‘operational boundary’. The authorised limit is the maximum level of borrowing that can be outstanding at any one time. The limit is a statutory requirement as set out in the Local Government Act 2003. The limit includes ‘headroom’ for unexpected borrowing resulting from adverse cash flow.
The operational boundary represents the level of borrowing needed to meet the capital investment plans approved by the council. Effectively it is the authorised limit minus the headroom and is used as an in-year monitoring indicator to measure actual borrowing requirements against budgeted forecasts.
Table 3 compares both indicators with the maximum debt outstanding in the first half year.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enc. 1 for Treasury Management Policy Statement 2016/17 (including Annual Investment Strategy 2016/17) –Mid Year ReviewReport | 215 KB | DownloadRead as text |
PDF |
Enc. 2 for Treasury Management Policy Statement 2016/17 (including Annual Investment Strategy 2016/17) –Mid Year ReviewReport | 105 KB | Download |
PDF |
Treasury Management Policy Statement 2016/17 (including Annual Investment Strategy 2016/17) –Mid Year ReviewReport | 360 KB | Download |
PDF |
Treasury Management Policy Statement 2016/17 (including Annual Investment Strategy 2016/17) –Mid Year ReviewReport | 216 KB | Download |
PDF |
View as HTML (67./2) 39 KBReport | 39 KB | Download |
PDF |
View as HTML (67./3) 18 KBReport | 18 KB | Download |
PDF |
View item 67. as HTML 33 KBReport | 33 KB | Download |
Follow Audit & Standards Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Sep 2023 | Audit Findings Report 2022/23View the decision text for item 21. | Decided | Open |
| 26 Sep 2023 | Audited Statement of Accounts 2022/23View the decision text for item 22. | Decided | Open |
| 26 Sep 2023 | External Auditors Annual Report 2022/23View the decision text for item 23. | Decided | Open |
| 26 Sep 2023 | Internal Audit and Counter Fraud Quarter 1 Progress Report 2023/24View the decision text for item 24. | Decided | Open |
| 26 Sep 2023 | Standards UpdateView the decision text for item 25. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.