Major Projects Bulletin March 2018 61 Royal Pavilion Estate Architects: Feilden Clegg Bradley Studios
Estimated project value: £21.5M
What happened in the last period? Blockwork and drainage in new Corn Exchange and Studio Theatre basement Proposed scheme Repair and redecoration of external facades Background Erection of steel frame in Gallery area. Heritage Centre Stage is a bold and significant initiative by the Royal Pavilion & Museums (RPM) and Brighton Dome & Festival Ltd (BDBF) to What’s going to happen in the next period? reunite the historic Royal Pavilion Estate. Phase 1 of this ambitious Replacement of Corn Exchange roof regeneration of the Royal Pavilion Estate (RPE) will deliver a major On-going repair to Corn Exchange wooden frame 62
restoration of the nationally important Grade I listed Corn Exchange & Installation of new Air Handling Units on Dome roof Grade II listed Studio Theatre to enhance audience comfort & help the building operate more efficiently. This will include significant structural Installation of roof and walls of new Gallery building improvements that rationalise operations and drive increased revenue Continuing repair and redecoration of external facades surpluses in order to deliver against BDBF’s ambitious business plan. Completion of Conservation Plan and Management & Achievement of this plan is central to our vision for the Royal Pavilion Maintenance Plan for RP Garden Estate and its future contribution to the cultural and economic wellbeing Consultation on Phase 2 Garden improvement proposals. of Brighton & Hove. Phase 2 is now being considered and will aim to deliver significant restoration and improvement works to the Royal Target Milestones Pavilion and Garden. Phase 1 works complete Autumn 2018 Key Facts Phase 2 Round 1 HLF bid submitted June 2018 Phase 2 Round 2 HLF bid submitted September 2019 Current stage: Phase 1 (Corn Exchange & Studio Theatre) started on Phase 2 works (Garden) SoS Autumn 2019 site February 2017 Phase 2 works (Royal Pavilion) SoS Autumn 2020 Partners: Brighton & Hove City Council, Brighton Dome & Brighton Project complete Autumn 2022 Festival, Arts Council England, Heritage Lottery Fund and Coast to Capital LEP Brighton Waterfront Estimated project value: c£540M
Outputs:
2,000 jobs New venue & conference centre Improve & expanded destination shopping Improved public realm The Brighton Centre and Churchill Square Black Rock Housing and office space Background What happened in the last period? We’re finalising details of a legal agreement which will deliver a Legal and commercial discussions on the Conditional Land major new conferencing and events venue for Brighton & Hove on Acquisition Agreement (CLAA) have continued to progress well. the Black Rock site next to the Marina and an expansion of Churchill 63
Square shopping centre. What’s going to happen in the next period? Key Facts An exchange of the CLAA is targeted for March 2018.
Current stage: Target Milestones Closure of legal and commercial negotiations CLAA agreed - March 2018 Planning – 2020/21 Partners:
Brighton & Hove City Council and Standard Life Aberdeen
Architects:
ACME Space, David Leonard Associates (central site) King Alfred Development Partners: Brighton & Hove City Council, Crest Nicholson & the Starr Trust Architects: LA Architects – Sports centre and Haworth Tompkins – Wider scheme and master plan Estimated project value: c£250M Outputs:
Proposed Scheme Current King Alfred Leisure Centre New sports centre of c12,000 M2 565 homes (20% affordable) Background Commercial/retail space Community and public space In 2014 the Council embarked on a procurement exercise to bring about the comprehensive redevelopment of the 1.8 hectare King What happened in the last period? 64
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Major Projects UpdateReport | 523 KB | DownloadRead as text |
PDF |
View item 58. as HTML 352 KBReport | 352 KB | Download |
Follow Tourism, Development & Culture Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jun 2019 | Madeira Terrace Restoration - Petition response and next stepsView the decision text for item 8. | Decided | Open |
| 20 Jun 2019 | Constitutional Matters- Tourism, Development & Culture CommitteeView the decision text for item 9. | Decided | Open |
| 20 Jun 2019 | Royal Pavilion and Museums Service - moving to TrustView the decision text for item 10. | Decided | Open |
| 20 Jun 2019 | Sports Facilties ContractView the decision text for item 11. | Decided | Open |
| 20 Jun 2019 | Hollingbury Park and Waterhall Golf CoursesView the decision text for item 12. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.