Resolved
View the decision text for item 122.
2.1That committee notes the commencement of an options programme in relation to the future delivery of repairs, planned maintenance and capital works for the council’s housing stock, as detailed in the body of this report.
187 3. CONTEXT/ BACKGROUND INFORMATION
3.1The council entered into a ten year partnering contract with Mears Limited in March 2010. The contract covers the majority of repairs, planned maintenance and capital works undertaken to the council owned housing stock.
3.2The expiry of the current contract provides an opportunity to deliver substantial change in relation to these services and works for our residents, stakeholders and the council as a whole.
3.3At this stage decisions have not been made about how the services and works will be delivered following the expiry of the contract. Over the coming months officers will work with residents and members to shape options for the future delivery of these important services. Proposals will then move forward through the council’s governance process including Housing Area Panels and the appropriate committees.
3.4The options programme will be managed by a programme board led by the Executive Director for Neighbourhoods, Community and Housing. Regular update reporting will be delivered to the Procurement Advisory Board (with Housing lead members in attendance).
3.5Reports will be presented to committees in line with the table at paragraph 3.7. Regular briefing will be delivered to members and other stakeholders alongside the progression of the options programme.
3.6Specialist consultants have been engaged to deliver an initial options and market research report for consideration by the programme board. This will provide an indication of the options available for the delivery of the services and works and the associated risks and opportunities.
3.7The indicative timetable below indicates the high level process for this programme and committee reporting to Housing and New Homes Committee and Policy, Resources and Growth Committee. Consultation with the Housing Area Panels is also integral to this process:
Date Actions
February 2018 Initial briefing to Area Panels
March 2018 Initial report to Housing & New Homes Committee
April 2018 Start of resident engagement activities
April – August 2018 Continued development of procurement/other options strategy and specification with residents, members and officers.
June – October 2018 Approval of preferred options, delivery scope and any authority to tender required through Housing & New Homes Committee and Policy, Resources and
188 Growth Committee
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Procurement programme for housing repairs, planned maintenance and capital worksReport | 263 KB | DownloadRead as text |
PDF |
Procurement programme for housing repairs, planned maintenance and capital worksReport | 227 KB | Download |
PDF |
View as HTML (122./2) 48 KBReport | 48 KB | Copy on its way |
PDF |
View item 122. as HTML 36 KBReport | 36 KB | Copy on its way |
Follow Policy, Resources & Growth Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 18 Jul 2019 | BAi360 June 2019 PaymentView the decision text for item 6. | Decided | Open |
| 18 Jul 2019 | Targeted Budget Management (TBM) Provisional Outturn 2018/19View the decision text for item 7. | Decided | Open |
| 18 Jul 2019 | Targeted Budget Management (TBM) 2019/20: Month 2View the decision text for item 8. | Decided | Open |
| 18 Jul 2019 | Treasury Management STrategy Statement 2018/19 - End of Year ReviewView the decision text for item 9. | Decided | Open |
| 18 Jul 2019 | Revenue & Capital Budget Planning and Resource Update 2020/21 to 2023/24View the decision text for item 10. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.