Resolved
View the decision text for item 40.
Audit & Standards Committee decided this item on Tuesday 14 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 40.
Internal Audit Report Valley Gardens Phase 3
Assignment Lead: Alex McLaren, Principal Auditor Assignment Manager: Mark Dallen, Audit Manager Prepared for: Brighton & Hove City Council Date: November 2019
57 Internal Audit Report – Valley Gardens Phase 3
Report Distribution List
Geoff Raw, Chief Executive Nick Hibberd, Executive Director Economy Environment & Culture Abraham Ghebre-Ghiorghis, Executive Lead Officer Strategy Governance & Law David Kuenssberg, Executive Director Finance & Resources Mark Prior, Assistant Director City Transport
Audit and Standards Committee
This audit report is written for the officers named in the distribution list. If you would like to share it with anyone else, please consult the Chief Internal Auditor.
Brighton & Hove City Council - Internal Audit Key Contact Information Chief Internal Auditor: Russell Banks, 01273 481447, [email protected] Audit Manager: Mark Dallen, 01273 291314, [email protected] Anti-Fraud Hotline: 01273 291700, [email protected]
Brighton & Hove City Council Page 2
58 Internal Audit Report – Valley Gardens Phase 3
1. Introduction
1.1Valley Gardens is the name given to the green spaces that run from St Peter’s Church to the Palace Pier.
1.2The northern section of Valley Gardens is referred to as ‘Phase 1 (St Peter’s)’ and ‘Phase 2 (Victoria Gardens)’. Phase 3 refers to the area from the Old Steine to the Palace Pier roundabout, the estimated cost of Phase 3 in the council’s business case is £7.84 million.
1.3The core objectives for Valley Gardens Phase 3 (VG3) were approved by the Environment, Transport and Sustainability (ETS) committee in June 2018. Design options for the area were then developed and a single, preferred design option was presented to the committee on 9 October 2018, as was explained within the June 2018 report. Committee members gave approval for Council officers to undertake further development work on the design and hold a public consultation.
1.4A public consultation took place from 15 October to 25 November 2018, the results of which were reported to ETS committee in January 2019. Approval of the Final Preliminary Design of Phase 3 was given by the council’s ETS Committee in February 2019.
1.5This desk top review was requested by Councillors at the July 2019 Audit & Standards Committee, following the receipt of a letter presented by Cllr. Lee Wares, setting out a number of concerns regarding the management of the project and the information provided to members. This audit is therefore an additional review to the agreed internal audit plan for 2019/20. A copy of this letter is separately attached as Annex B.
2. Scope
2.1The Audit & Standards Committee requested ‘a desktop audit limited in scope to the questions of whether the Council had correctly followed processes and procedures’. Our interpretation of this request was that our review should focus on making sure that appropriate decision making arrangements were in place, including the accuracy and transparency of information provided to Members. Specifically our review focused on the following which align to concerns raised in Cllr. Wares letter:
1. Whether information about £6m of LEP funding, as contained in the Committee report (7 February), was correct at the time of report writing.
2. To consider whether accurate information has been communicated to Members about the implications of delays on the funding of the project.
3. To identify whether key projects which closely relate to the VG3 have been transparently reported to Members and the LEP.
4. To ascertain if there has been any traffic or environment assessment of the VG3 project.
5. To review the approach taken to stakeholder engagement and the consultation process relating to VG3.
Brighton & Hove City Council Page 3
59 Internal Audit Report – Valley Gardens Phase 3
3. Methodology
3.1This review has focussed on an examination and analysis of the following:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Valley Gardens Project (Phase 3) APX. n 1Report | 664 KB | DownloadRead as text |
PDF |
Valley Gardens Project (Phase 3)Report | 133 KB | Download |
PDF |
View as HTML (40./2) 100 KBReport | 100 KB | Download |
PDF |
View item 40. as HTML 30 KBReport | 30 KB | Download |
Follow Audit & Standards Committee at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 26 Sep 2023 | Audit Findings Report 2022/23View the decision text for item 21. | Decided | Open |
| 26 Sep 2023 | Audited Statement of Accounts 2022/23View the decision text for item 22. | Decided | Open |
| 26 Sep 2023 | External Auditors Annual Report 2022/23View the decision text for item 23. | Decided | Open |
| 26 Sep 2023 | Internal Audit and Counter Fraud Quarter 1 Progress Report 2023/24View the decision text for item 24. | Decided | Open |
| 26 Sep 2023 | Standards UpdateView the decision text for item 25. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.