Greater Brighton Economic Board decided this item on Tuesday 28 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
View the decision text for item 26.
Greater Brighton Economic Board
Investment Programme Update 87
Report
28th January 2020 Contents Item 1 Highlight Summary Page 3 2 Adur Civic Centre – Shoreham Page 4 3 Burgess Hill Strategic Growth Programme Page 5 4 Central Research Laboratory - Brighton Page 7 5 Circus Street- Brighton Page 8 6 Decoy Farm - Worthing Page 9 7 Digital Catapult- Brighton Page 10 9 Eastside South - Newhaven Page 11 10 Heritage Centre Stage - Brighton Page 12 11 New England House - Brighton Page 13 88
12 New Monks Farm – Shoreham By Sea Page 14 13 Flood Alleviation Scheme - Newhaven Page 15 14 Port Access Road - Newhaven Page 16 15 Railway Quay - Newhaven Page 17 16 Springman House - Lewes Page 18 17 Teville Gate - Worthing Page 19 18 Union Place - Worthing Page 20 19 Valley Gardens - Brighton Page 21 20 Waterfront Brighton Page 22 21 Western Harbour Arm – Shoreham-By-Sea Page 23
2 Investment Programme Update January 2020 Highlight Summary
PROJECT DELIVERY PARTNERS REPORT HIGHLIGHT The third cohort of businesses for the 5G Brighton Technology Accelerator Programme has been selected. It includes Wired Sussex & University of Brighton, firms developing drone management systems for undertaking complex maintenance tasks in challenging Digital Catapult University of Sussex, BHCC, American Express environments, real-time mobile translation and subtitling technology, and live VR access to international tourist Brighton destinations. The founders’ room and bar at the Dome has now been fitted with 5G connectivity. The first set of cultural and creative use-cases that will develop ideas using it and the FuseBox are currently under consideration
Brighton & Hove City Council’s land deal with Maplebright and Legal & General (L&G) on the adjacent Longley Industrial Estate was completed at the end of November 2019. New England Brighton & Hove City Council On 5 December 2019 the council’s Policy, Resources & Growth Committee (PR&G) agreed for design work and House 89
financial modelling to be undertaken. These areas of work will be progressed in consultation with key stakeholders, with a further check-in with PR&G later in 2020, prior to the next stages of work being undertaken (including a planning application and project implementation).
The demountable flood barrier over the A26 has now been successfully completed. Substantial progress on the rail Newhaven Flood Environment Agency, Lewes DC, Coast to Capital flood barrier together with Network Rail has been made, with 90% of all works now completed. Works on this aspect Alleviation LEP, South East LEP. of the scheme are anticipated to commence in June 2020, subject to final legal agreements. Scheme
Teville Gate Construction commenced on new office building for Teville Gate House and topping-out took place in December Worthing Borough Council, Mosaic Global (Worthing 2019. Investments, Coast to Capital LEP, Hanson Central Phase1) Developments & HMRC, Homes England Mosaic Capital has submitted their application. Expected for decision at March planning committee.
3 Investment Programme Update January 2020 Adur Civic Centre - Shoreham
Funding (all years) Total LGF Funding £1.71m
Total Public Funding £0.0m
Total Private Funding £9.89m
Total Other Funding £0.00m
Total Funding £11.60m
Outputs Phase 1 North Site -30,000sqft of employment space 90
Phase 2 South Site – 987sqm of employment space and 171 residential units
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Greater Brighton Investment Programme: Progress Update APX. n 1Report | 2.7 MB | DownloadRead as text |
PDF |
Greater Brighton Investment Programme: Progress UpdateReport | 486 KB | Download |
PDF |
View item 26. as HTML 39 KBReport | 39 KB | Download |
Follow Greater Brighton Economic Board at Brighton and Hove and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Apr 2025 | Sussex Energy UpdateView the decision text for item 20. | Decided | Open |
| 2 Apr 2025 | Greater Brighton Operational Arrangements 2025/26View the decision text for item 21. | Decided | Open |
| 2 Apr 2025 | Strategic Workplan 2025/26View the decision text for item 22. | Decided | Open |
| 16 Oct 2024 | Sussex Energy UpdateView the decision text for item 9. | Decided | Open |
| 16 Oct 2024 | Admission of New Member to the BoardView the decision text for item 10. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.