Brighton and Hove City Council
Housing Committee, Wednesday 17 June 2020 at 4.00pm

Solar PV programme for HRA Housing stock

Approved Committee 8 papers

Housing Committee approved this item on Wednesday 17 June 2020. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That Housing Committee: 2.1 Delegates authority to the Executive Director, Housing Neighbourhoods & Communities to take all steps necessary to: 2.1.1 procure and award a contract for the installation of a minimum of 500 and a maximum of 1000 domestic solar PV arrays for the period 2020-2023 , the budget for the first 500 to be allocated as set out in 2.2. below, with the additional 500 to be commissioned subject to grid and contractor capacity as referred to in paragraphs 4.18-4.20 below and to the necessary additional budget approval from Policy & Resources Committee ; 2.1.2 increase this to at least 25 00 installations by 2026 subject to further Committee approval of budget allocation and the constraints set out in paragraphs 4.18-4.20 in the report but mindful of the council having approximately 4000 domestic properties suitable for such arrays . 2.2 Recommend s Policy & Resources Committee allocate the following additional budget to allow for the delivery of the initial 500 domestic solar PV arrays for the period 2020-23: · 2021/22: £875k; · 2022/23: £875k; 2.3 requests that a report covering the scope to expand the solar PV programme be brought to Committee no later than the fourth quarter of 2021 i.e. ahead of 2022 Budget Council. That Housing Committee: 2.1 Delegates authority to the Executive Director, Housing Neighbourhoods & Communities to take all steps necessary to: 2.1.1 procure and award a contract for the installation of a minimum of 500 and a maximum of 1000 domestic solar PV arrays for the period 2020-2023 , the budget for the first 500 to be allocated as set out in 2.2. below, with the additional 500 to be commissioned subject to grid and contractor capacity as referred to in paragraphs 4.18-4.20 below and to the necessary additional budget approval from Policy & Resources Committee ; 2.1.2 increase this to at least 25 00 installations by 2026 subject to further Committee approval of budget allocation and the constraints set out in paragraphs 4.18-4.20 in the report but mindful of the council having approximately 4000 domestic properties suitable for such arrays . 2.2 Recommend s Policy & Resources Committee allocate the following additional budget to allow for the delivery of the initial 500 domestic solar PV arrays for the period 2020-23: · 2021/22: £875k; · 2022/23: £875k; 2.3 Requests that a report covering the scope to expand the solar PV programme be brought to Committee no later than the fourth quarter of 2021 i.e. ahead of 2022 Budget Council.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Housing Committee

Housing Committee Agenda Item

Brighton & Hove City Council

Appendix 1: PRIORITSATION OF PROPERTIES FOR INSTALL This appendix sets out the proposed approach to ensure an equitable distribution of solar PV systems amongst tenants. It is a process by which properties are firstly deemed technically feasible and then prioritised. Technical feasibility criteria The following must all be true for a house or bungalow to be considered technically feasible for installation: Reason for exclusion Justification Notes 43

Property is not a house or Unsuitable for solar PV system SOLARISE project aims to benefit tenants within blocks. bungalow Property does not have an Yield from solar panels facing Very few houses only have a North facing roof (i.e. most will East, South or West-facing North not cost effective in terms of also have a south facing roof). roof generation potential Needs reroofing Not cost effective to remove Could install solar PV when reroofing occurs as part of re- panels for reroofing in medium- roofing programme (not currently part of the reroofing term specification) or as part of a future solar PV programme Structural issues with the roof Unsuitable for solar PV system Unlikely that there is a cost-effective resolution to this but potential to re-visit if structural issues are addressed UKPN reject grid connection Unsuitable for solar PV system In due course, UKPN will upgrade the distribution network in application due to capacity an area, at which point installs can recommence locally. constraints in the area* Practically the entire city is classed as having ‘limited capacity’ and so this is a risk across all areas *note that as there is a cost to make a grid connection application, this will not be known until after the prioritisation and tenant engagement work has been conducted. Technically feasible properties will then be prioritised based on a range of measures that indicate that the occupant is more likely to be paying higher energy bills or struggling to pay their energy bills but based on property type and area rather than specific householder eligibility:

Priority Justification 1. Property’s current EPC is D or worse Fuel bills likely to be higher than majority of the Council Housing stock. This can be revised (i.e. to EPC C) once most Eligible D and E properties are completed 2. Property has electric heating Fuel bills likely to be higher than properties heated with gas, and potential for greater benefit from the generated electricity 3. Priority for properties in an LSOA within the Tenants at greater risk of fuel poverty city’s top 29 for Indices of Deprivation 44

No prioritisation will be based on:  Roof orientation, height or shading…all of which impact on:  System performance  Location (aside from fuel poor areas)

Note: We have not proposed a more specific targeting approach based on individual eligibility of householders i.e. in receipt of certain benefits due to the potential for labelling those households via the solar PV install. The above property based approach also ensures that the property itself is future-proofed for reducing fuel bills for future occupants in addition to existing occupants.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Housing Cmt: 17 June 2020 Amendment to Agenda Item 8Agenda 123 KB Download
PDF
Solar PV programme for HRA Housing stock APX. n 1Report 306 KB DownloadRead as text
PDF
Solar PV programme for HRA Housing stock APX. n 2Report 247 KB Download
PDF
Solar PV programme for HRA Housing stockReport 196 KB Download
PDF
View as HTML (8./2) 14 KBReport 14 KB Download
PDF
View as HTML (8./3) 120 KBReport 120 KB Download
PDF
View as HTML (8./4) 14 KBAgenda 14 KB Download
PDF
View item 8. as HTML 34 KBReport 34 KB Download

At this meeting

Whole meeting

More from Brighton and Hove Housing Committee

All decisions
MeetingDecisionOutcome
15 Mar 2023 Private Sector Housing: Discretionary licensing evidence2.1 That Housing Committee notes the findings of the Private Sector Housing: Housing Stock Condition & Stressors Repo... Approved Open
15 Mar 2023 Housing Repairs and Maintenance – Procurement of Materials Supply ChainThat Housing Committee delegates authority to the Executive Director of Housing, Neighbourhoods and Communities to: 2... Approved Open
15 Mar 2023 Housing Management Area Panel Review2.1 Approves the revised Terms of Reference for Housing Area Panels in Appendix 1. 2.2 Recommends to Policy & Resourc... Approved Open
15 Mar 2023 Homes for Brighton & Hove – external communal area management at Coldean Lane, Brighton.That Housing Committee: 2.1 Recommends to Policy & Resources Committee that it delegates authority to the Executive D... Decided Open
15 Mar 2023 Develop a policy to incentives households to relinquish council tenancies as an alternative to right to buy2.1 That Housing Committee note this report. 2.2 That Housing Committee agree to a full report coming back to a futur... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies