Internal Audit Annual Report and Opinion 2025/26

Decided Finance 4 papers

AI summaryBrighton and Hove Audit, Standards and General Purposes Committee received the Internal Audit Annual Report giving a partial assurance opinion on the council's governance, risk management and internal control framework for 2025/26.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFor the period 1 April 2025 to 31 March 2026
MoneyNot stated
What happens nextFollow-up audits and enhanced reviewsOn Council Tax and Accounts Receivable in 2026/27
Who it affectsCouncil services, schools, taxpayersFinancial systems, building maintenance, schools

What was decided

The committee received the Internal Audit Annual Report and Opinion for 2025/26, in which the Chief Internal Auditor gave a partial assurance opinion on the council's framework of governance, risk management and internal control. Report 3.1, 3.2

The committee noted that one minimal assurance opinion (Reactive and Planned Maintenance) and twelve partial assurance opinions were issued during 2025/26, including three schools. Report 5.5, P34, P35

The committee noted the report's findings that the council's key financial systems of Council Tax and Accounts Receivable (Debtors) received only partial assurance, with capacity and resilience challenges identified across services. Report 5.10, 5.14, 5.7

Why

Statutory duty under the 1972 Local Government Act and the Accounts and Audit Regulations 2015 requires the Chief Internal Auditor to give an annual opinion to support the Annual Governance Statement. Report 1.1, 1.3

Although the majority of opinions were positive, a high number of partial assurance reports and weaknesses in key financial and service areas drove the partial overall opinion. Report 3.2, 5.5

Capacity challenges, service resilience issues, and ongoing financial pressures continue to affect the implementation of agreed actions and the control environment. Report 5.7, 5.9

What happens next

Management will take prompt action on findings, with root cause reviews and actions added to the Transformation and Innovation Portfolio, the Annual Governance Statement and the Corporate Leadership Plan. Report 3.5

All partial and minimal assurance audits will be followed up, normally within 12 months, with enhanced follow-ups planned on Council Tax and Accounts Receivable in 2026/27. Report 5.8, 5.15

The 2026/27 audit plan will continue to focus on the council's key financial systems, building maintenance, and emerging technology and cyber risks. Report 5.16, 5.28, 5.29

Options considered

  • Chosen: Provide partial assurance opinion for 2025/26. Based on the balance of mostly positive opinions but a high number of partial assurance reports and identified control weaknesses, particularly in key financial systems and building maintenance. Report 3.1, 3.2, 5.5
  • Rejected: Provide substantial or reasonable assurance opinion. Not supported by the high number of partial and one minimal assurance opinions in key financial and service areas. Report 3.1, 5.5

Implications

  • Risk: Partial assurance opinion means weaknesses in the control environment put some system or service objectives at risk, particularly in financial systems and building maintenance. Report 3.1, P111, 5.10
  • Financial: Council Tax collection rate forecast was reduced at the time of the audit, and rising debt in Adult Social Care required a strategic review. Report 5.14
  • Staffing: Capacity challenges and service resilience have been identified as root causes of control weaknesses, compounded by demand and recruitment and expenditure controls. Report 5.7
  • Risk: Cyber-attack risk is increasing nationally, and an audit on cyber security in schools was added to the plan in response to local and national incidents. Report 5.29
  • Other: A dedicated project management resource and a new Board are being set up in 2026-27 to drive the programme to improve corporate financial systems. Report 5.11

Who and where

  • Council Taxpayers and residents receiving services Report 5.14
  • Adult Social Care service users (rising debt levels)
  • Schools (St Andrews Primary, Tarnerland Nursery, Elm Grove Primary, Middle Street Primary) Report 5.5, P34, P35
  • Council departments responsible for key financial systems, building maintenance and housing repairs Report 5.10, 5.22
  • Corporate Leadership Team and the Audit, Standards and General Purposes Committee (oversight) Report 2.2, 3.5

Timeline

  • 1 April 2025 to 31 March 2026: Period covered by the internal audit opinion Report 3.1
  • 1 April 2025: New Global Internal Audit Standards (GIAS) replaced the Public Sector Internal Audit Standards (PSIAS) Report 6.1
  • 22 April 2025: Internal Audit Strategy and Annual Audit Plan (2025/26) approved by the Audit, Standards and General Purposes Committee Report P86
  • 24 June 2025: 2024/25 Annual Report and Opinion presented to the Audit, Standards and General Purposes Committee Report P86
  • September 2025: Self-assessment against GIAS reported to the committee, identifying only minor areas for improvement Report 6.5, P87
  • 23 June 2026: Internal Audit Annual Report and Opinion 2025/26 presented to the Audit, Standards and General Purposes Committee Report P2, 3.1
  • 2026/27: Enhanced follow-up reviews on Council Tax and Accounts Receivable planned Report 5.15

Plain English for the jargon

  • Partial assurance: Audit opinion meaning weaknesses in the system of control put the achievement of system or service objectives at risk.
  • Minimal assurance: Audit opinion meaning controls are generally weak or non-existent, leaving the system open to significant error or fraud.
  • Reasonable assurance: Audit opinion meaning most controls are in place and operating as expected to manage key risks.
  • Substantial assurance: Audit opinion meaning controls are in place and operating as expected to manage key risks.
  • PSIAS / GIAS: Public Sector Internal Audit Standards, replaced on 1 April 2025 by the new Global Internal Audit Standards.
  • HRA: Housing Revenue Account, the account landlords use to manage income and spending on social housing.
  • IR35: Off-payroll working rules that determine whether someone working through a personal service company should be taxed as an employee.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

View the decision text for item 9.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Audit, Standards & General Purposes Committee, 18 pages

Appendix 1

INTERNAL AUDIT ANNUAL REPORT & OPINION 2025/2026

Brighton & Hove City Council

75 1. Internal Control and the Role of Internal Audit

1.1All local authorities must make proper provision for internal audit in line with the 1972 Local Government Act (S151) and the Accounts and Audit Regulations 2015. The full role and scope of the Council’s Internal Audit Service is set out within our Internal Audit Charter.

1.2It is a management responsibility to establish and maintain internal control systems and to ensure that resources are properly applied, risks appropriately managed and outcomes achieved.

1.3Annually the Chief Internal Auditor is required to provide an overall opinion on the Council’s internal control environment, risk management arrangements and governance framework to support the Annual Governance Statement.

2. Delivery of the Internal Audit Plan

2.1The Council’s Internal Audit Strategy and Plan is updated each year based on a combination of management’s assessment of risk (including that set out within the departmental and strategic risk registers) and our own risk assessment of the Council’s major systems and other auditable areas. The process of producing the plan involves extensive consultation with a range of stakeholders to ensure that their views on risks and current issues, within individual departments and corporately, are identified and considered.

2.2In accordance with the audit plan for 2025/26, a programme of audits was carried out in accordance with best practice, this programme was reviewed during the year and revised to reflect changes in risk and priority. All adjustments to the audit plan were agreed with the relevant departments and reported throughout the year to the Corporate Leadership Team and the Audit, Standards and General Purposes Committee as part of our periodic internal audit progress reports. Full details of the adjustments to the plan can be found in Appendix D.

2.3It should be noted that whilst there were some audit reports in progress or at draft report stage at year-end, outcomes from this work have been considered in forming our annual opinion. Full details of these audits will be reported to the Corporate Leadership Team and the Audit, Standards and General Purposes Committee once each of the reports have been finalised with management.

3. Audit Opinion

3.1No assurance can ever be absolute; however, based on the internal audit work completed, the Chief Internal Auditor can provide partial (1) assurance that the Council has in place an adequate and effective framework of governance, risk management and internal control for the period 1 April 2025 to 31 March 2026.

3.2Further information on the basis of this opinion is provided below. Although the majority of audit opinions issued in the year were generally positive, there are still a high number of partial assurance reports overall and internal audit activities have

1 This opinion is based on the activities set out in the paragraphs below. It is therefore important to emphasise

that it is not possible or practicable to audit all activities of the Council within a single year.

76 identified a number of key areas where the operation of internal controls has not been fully effective. A number of these relate to key financial or key services and link to risks identified in the Council’s strategic risk register.

3.3Internal Audit work closely with management and discuss areas of risk and focus for our audit work. This means that we do receive requests from management for audit work and we will consider these, alongside the risk profile for the Council. Sometimes this is a request in order to obtain assurance over areas where there are known issues and a potential need for improvement. This demonstrates a positive organisational culture which utilises Internal Audit to help support service improvement.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Audit Annual Report and Opinion 2025/26 APX. n 1Report 18 pages DownloadRead as text
PDF
Internal Audit Annual Report and Opinion 2025/26Report 4 pages Download
PDF
View as HTML (9./2) 125 KBReport 125 KB Copy on its way
PDF
View item 9. as HTML 37 KBReport 37 KB Copy on its way

At this meeting

Whole meeting

On this subject at Brighton and Hove

Search all
  1. Internal Audit Annual Report and Opinion 2025/26This decision
  2. Internal Audit and Counter Fraud Quarter 4 Progress Report 2025/26Decided
  3. Internal Audit Strategy and Annual Audit Plan 2026-27Decided
  4. Internal Audit and Counter Fraud Quarter 3 Progress Report 2025/26Decided
  5. Internal Audit and Counter Fraud Quarter 2 Progress Report 2025/26Decided
  6. CIPFA Code of Practice for the Governance of Internal Audit in UK Local GovernmentDecided

More from Brighton and Hove Audit, Standards & General Purposes Committee

All decisions
MeetingDecisionOutcome
23 Jun 2026 External Audit Plan 2025/26View the decision text for item 7. Decided Open
23 Jun 2026 Informing the Audit Risk Assessment 2025/26View the decision text for item 8. Decided Open
23 Jun 2026 Counter Fraud Annual Report 2025/26View the decision text for item 10. Decided Open
23 Jun 2026 Counter Fraud StrategyView the decision text for item 11. Decided Open
23 Jun 2026 Formal approval of the Annual Governance Statement 2025-2026View the decision text for item 12. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies