Brighton and Hove City Council
Cabinet, Thursday 15 October 2026 at 10.30am

Royal Pavilion Gardens Restoration Project

Decided Executive 2 papers

AI summaryBrighton and Hove Cabinet approves £1.600m budget increase for Royal Pavilion Garden restoration, taking total project cost to £8.038m and paving the way for main contractor appointment.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedCabinet approved £1.600m uplift and delegated contract award
Money£8.038m total project budgetFunded by NLHF, Historic England, council and RPMT
What happens nextContract execution 22 October 2026Estimated work start 9 November 2026
Who it affectsRoyal Pavilion Garden visitors and residentsRestoration, new toilets, accessibility and biodiversity gains

What was decided

Cabinet agreed a £1.600m budget increase, taking the total project cost to £8.038m, funded by National Lottery Heritage Fund grant, a Historic England grant and Royal Pavilion and Museums Trust donations. Report 2.1, 3.15

Cabinet delegated authority to the Corporate Director for City Operations, in consultation with the relevant Cabinet Member, to enter into a contract with the preferred main contractor Blakedown Landscapes within the project cost plan, subject to confirmation of the additional £0.500m Historic England funding. Report P2, 3.12, 3.13

Why

Project costs rose during design development because of COVID-19 delays, construction inflation, higher material costs and additional professional fees, leaving the tender result about £1.476m above the funding already awarded. Report 3.9, 3.10, 3.11, 3.14

The Garden has been on Historic England's Heritage at Risk Register since 2017, and the restoration is intended to secure its long-term conservation, improve accessibility and enhance biodiversity. Report 3.3, 3.8, 10.1, 14.2

No additional direct council funding is requested, and identified funding exceeds the budget, giving some flexibility if expected external fundraising is not secured. Report 3.18, P19

What happens next

If the additional Historic England £0.500m is confirmed and the contract is executed on 22 October 2026, work on site is expected to start on 9 November 2026 and complete by November 2027. Report 3.19, P28, P29

The Project Team will continue value engineering, manage a 12.5% works and 7.5% other-costs contingency, and pursue further external funding including an £0.085m Arts Council England bid and RPMT fundraising. Report 3.13, 3.17, 6.4

The money

  • £1.600m Budget increase approved by Cabinet Report 2.1, 6.1
  • £8.038m Revised total project budget Report 2.1, 3.15
  • £6.437m Current council capital programme budget for the project Report 6.1
  • £0.750m Total approved council capital contribution to the project Report 3.6, 6.1, 6.5
  • £0.440m Council share funded through borrowing Report 6.1, 6.5
  • £0.046m Estimated annual borrowing costs at PWLB rates on 2 October 2026 Report 6.5
  • £0.500m Historic England grant application awaiting decision Report 3.14, 3.17, 6.2
  • £0.976m Additional National Lottery Heritage Fund grant awarded Report 3.14
  • £0.550m Secured NLHF grant within the £1.600m increase Report 6.2
  • £0.550m RPMT donations within the £1.600m increase still to be secured Report 6.2
  • £0.085m Application to Arts Council England Report 3.17
  • £5.174m Proposed main contract sum with Blakedown Landscapes Report 3.13
  • £1.476m Tender shortfall above previously secured funding Report 3.14
  • £0.024m Estimated annual reduction in council management costs after refurbishment Report 3.16
  • £0.091m Total operating costs in 2025 Report 3.16
  • £50k Public Health commitment to City Safe Zone pilot Report 13.4
  • £35k Match funding leveraged from citywide stakeholders for City Safe Zone pilot Report 13.4

Options considered

  • Chosen: Proceed with full restoration at £8.038m using secured and anticipated funding. Delivers agreed heritage, accessibility and biodiversity outcomes and removes the Garden from the Heritage at Risk Register Report 2.1, 3.15, 14.1, 14.4
  • Rejected: Reduce project scope to fit within currently secured funding if the £1.050m unconfirmed money is not received. List of removable work packages prepared as a fallback only; would limit the project's approved purposes Report 4.2, 6.3
  • Rejected: Delay the project start so the ice rink can return over winter 2026/2027. Works will be on the ice rink site throughout winter and delay would create significant cost and funding implications Report 4.3

Implications

  • Financial: Total project cost is £8.038m; the council's contribution stays at £0.750m (£0.440m borrowing) with about £0.046m annual financing costs built into the MTFS. Report 3.15, 6.1, 6.5
  • Financial: If external funding is not secured, scope will be reduced to stay within the adjusted budget and protect the council's financial position. Report 4.2, 6.3
  • Financial: Refurbished toilets and a new concession leased to RPMT are expected to cut the council's ongoing management costs by about £0.024m a year. Report 3.16
  • Legal: Contract will be procured under the Procurement Act 2023 using a JCT Intermediate Building Contract 2024 with a bespoke Schedule of Amendments, and the council's Contract Standing Orders will apply. Report 7.1, 7.2, P50
  • Risk: Cost and programme risks will be managed through detailed design, surveys, value engineering, contingency, and equal sharing of any overspend beyond contingency between the council and RPMT under the Collaboration Agreement signed in September 2026. Report 6.4, 8.1, 8.2, 8.3, 8.4
  • Equalities: A Changing Places toilet accessed through the RADAR Key scheme will be provided at no charge, supporting the Accessible City strategy and disabled visitors. Report 9.1, 11.1
  • Equalities: Improved educational space, an Activity Plan and a new Community Forum will widen access for schools and marginalised groups. Report 9.2
  • Climate: Works will restore Regency planting, reinstate historic railings, protect and promote local biodiversity, and secure the Garden's long-term conservation in line with the Conservation Plan and a costed Management and Maintenance Plan. Report 3.8, 10.1, 10.2
  • Staffing: The design team, including a Clerk of Works role, will stay engaged throughout construction to oversee quality and resolve issues early. Report 8.5
  • Other: A City Safe Zone pilot with visible safety marshals, outreach and night-time economy work will address antisocial behaviour in the Garden, funded by £50k from Public Health and £35k matched from citywide stakeholders. Report 13.1, 13.2, 13.3, 13.4, 13.5

Who and where

  • Visitors and residents of Brighton and Hove using the Royal Pavilion Garden Report 3.8, 14.1
  • Disabled people who will benefit from a new Changing Places toilet and improved accessibility Report 9.1, 11.1
  • Schools and community groups engaging through the Activity Plan and Community Forum Report 5.3, 9.2
  • Royal Pavilion and Museums Trust (RPMT) as leaseholder and joint delivery partner Report 3.1, 6.4
  • Local businesses and night-time economy venues involved in the City Safe Zone pilot Report 13.2, 13.3
  • Main contractor Blakedown Landscapes, preferred tenderer for the restoration works Report 3.12, 3.13

Timeline

  • 18 August 2014: Memorandum of Understanding signed to redevelop the Royal Pavilion Estate Report 3.1
  • November 2017: Policy, Resources & Growth Committee approved NLHF bid and £1.000m council capital Report 3.4
  • 2017: Garden placed on Historic England Heritage at Risk Register Report 3.3
  • August 2023: Strategy, Finance & City Regeneration Committee approved up to £0.250m for new toilets and delegated contractor appointment Report 3.6
  • 2023: First phase, restoration of Brighton Dome Corn Exchange and Studio Theatre, completed Report 3.2
  • 2024: Planning approval granted for Garden restoration Report 3.8
  • December 2025: Detailed design estimate of £8.228m total project cost Report 3.10
  • February 2026: Forecast project cost reduced to £7.139m after design, procurement and delivery review Report 3.11
  • 14 September 2026: Additional funding applications submitted Report P28
  • 21 September 2026: Legal implications cleared by council lawyer Report P50
  • 23 September 2026: Funding decisions expected Report P28
  • 02 October 2026: Financial implications cleared by council finance officer Report P46
  • 22 October 2026: Contract execution on receiving Cabinet approval Report P28
  • 09 November 2026: Estimated work start on site Report P28
  • November 2027: Estimated completion of restoration works Report P28

Plain English for the jargon

  • RPMT: Royal Pavilion and Museums Trust, the leaseholder and joint delivery partner for the project
  • NLHF: National Lottery Heritage Fund, the main external funder
  • Heritage at Risk Register: Historic England's list of heritage sites at risk of loss or deterioration
  • PWLB: Public Works Loan Board, the government body providing local authority borrowing
  • MTFS: Medium Term Financial Strategy, the council's multi-year budget plan
  • JCT Intermediate Building Contract (ICD 2024): Standard form of building contract used for the main works
  • Changing Places toilet: Larger accessible toilet for people with complex disabilities, accessed here via the RADAR Key scheme
  • City Safe Zone: Pilot partnership programme in the Garden to reduce antisocial behaviour and improve safety
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item56

Resolved

View the decision text for item 56.
Word for word from the decision Brighton and Hove published for this meeting. Source: democracy.brighton-hove.gov.uk

Follow this further

Built from Brighton and Hove's papers

What the report saysPro

Report to Cabinet

Recommendations

2.1Cabinet agrees a budget increase of £1.600m funded by National Lottery Heritage Funding, Historic England Grant and RPMT donations. This takes the total project to £8.038m for the delivery of the restoration project works.

7 2.2 Cabinet delegates authority to the Corporate Director – City Operations, in consultation with the Cabinet Member for Economy, Culture, Heritage and Tourism, to enter into a contract to appoint a Main Contractor to carry out the restoration works to the Royal Pavilion Garden within the project cost plan. Subject to receiving approval of additional £0.500m funding from Historic England.

3. Context and background information

3.1The Memorandum of Understanding signed by the council, Royal Pavilion and Museums Trust [RPMT] and Brighton Dome Brighton Festival on 18 August 2014 proposes to redevelop and improve the Royal Pavilion Estate as a world class cultural and heritage site by integrating the Royal Pavilion, Brighton Dome, Brighton Museum & Art Gallery, Corn Exchange and Studio Theatre with their historic setting, improving the world class centre piece of Brighton & Hove’s city centre. The capital works will seek not only to improve the Royal Pavilion Estate, but also restore some of the connectivity between Brighton Dome, the Brighton Museum & Art Gallery and the Royal Pavilion, which will enable further co-working in the future on the delivery of cultural events and celebration of the parties’ unique heritage.

3.2The improvement programme is being delivered in phases to enhance the visitor experience, conserve the Estate's heritage and improve the long-term sustainability of the council's freehold assets. The first phase, comprising the restoration of Brighton Dome's Corn Exchange and Studio Theatre, was completed in 2023.

3.3The Garden sits within land leased and managed by the Royal Pavillion and Museums Trust. Historic England placed the Garden on its Heritage at Risk Register in 2017 and since this time a programme to protect and maintain the Garden and its infrastructure has been in development. The restoration project has since been developed jointly by the council and RPMT to address the Garden's condition and secure its long-term future.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Royal Pavilion Gardens Restoration ProjectReport 284 KB DownloadRead as text
PDF
View item 56. as HTML 103 KBReport 103 KB Copy on its way

At this meeting

Whole meeting

Who was there

0 of 10 attended
BS
Councillor Bella SankeyChair, expected
JT
Councillor Jacob TaylorDeputy Chair, expected
MA
Councillor Mitchie AlexanderCommittee Member, expected
JA
Councillor Jacob AllenCommittee Member, expected
ED
Councillor Emma DanielCommittee Member, expected
DM
Councillor David McGregorCommittee Member, expected
TM
Councillor Trevor MutenCommittee Member, expected
AR
Councillor Alan RobinsCommittee Member, expected
TR
Councillor Tim RowkinsCommittee Member, expected
GW
Councillor Gill WilliamsCommittee Member, expected

On this subject at Brighton and Hove

Search all
  1. Royal Pavilion Gardens Restoration ProjectThis decision
  2. Royal Pavilion & Museums Trust Service Fee 2026-31Decided
  3. Royal Pavilion Museums Trust Loan AgreementDecided
  4. Royal Pavilion & Museums Trust Annual ReportDecided
  5. Royal Pavilion & Museums Trust Annual ReportDecided
  6. Royal Pavilion and Museums Trust - Plan for 2021/22Decided

More from Brighton and Hove Cabinet

All decisions
MeetingDecisionOutcome
15 Oct 2026 Advertising and SponsorshipView the decision text for item 57. Decided Open
15 Oct 2026 Black Rock Future Vision and meanwhile use.View the decision text for item 58. Decided Open
15 Oct 2026 Streetlighting Contract ExtensionView the decision text for item 59. Decided Open
15 Oct 2026 Targeted Budget Management (TBM) 2026/27 Month 5 (August)View the decision text for item 60. Decided Open
17 Sep 2026 Raising Professional Standards for Housing Staff & TenantsView the decision text for item 46. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies