Stoke Bishop, Westbury-on-Trym and Henleaze Neighbourhood Partnership decided this item on Monday 13 June 2016. Below is the council's own wording, with the papers it was decided on.
Resolved – 1. To fund up to £6,000 for trees from the NP’s CIL allocation, with the exact cost to be determined as soon as possible; 2. To fund £1,000 from the NP’s CIL funds for daffodils to be grown around the NP’s playgrounds; 3. To allocate the NP’s £1,500 Clean and Green budget as set out below - · Stoke Bishop - £500 hanging baskets; · W-o-T - £500 flower fund (WOTSOC); · Henleaze - £500 flora (details to be provided).
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Stoke Bishop, Westbury-on-Trym and Henleaze Neighbourhood Partnership
Recommendations
1. The Neighbourhood Committee is requested to agree to fund up to £6,000 for trees from the NP’s CIL allocation (please see section 5.1 below). The exact cost will be determined as soon as possible
2. The Neighbourhood Committee is requested to agree to fund £1,000 from the NP’s CIL funds for daffodils to be grown around the NP’s playgrounds (see 5.4 below).
3. The Neighbourhood Committee is requested to agree to the allocation of the NP’s £1,500 Clean and Green allocation as set out in 6.1 below.
Present: Sheila Preece, Alan Preece, Hilary Long, Gill Brown, Val Bishop, Clare Milne, Helen Furber, Eileen Poad, Stephanie French, Susan Mayer, Alan Aburrow, David Mayer, Duncan Venison (BCC), Alan Morris, Mildred Miller, Kevin Chidgley, Glenise Morgan, Gary Brentnall, Andrew McGrath
Apologies: Claire Campion-Smith,
Meeting Chaired by David Mayer –
1. Minutes and Matters arising from 14th January 2016 meeting:
Notes considered accurate with the following exceptions or continuing actions:
1.1Phoenix Lane Weeds. This is being picked up by BCC maintenance. Action: Gary to check. 1.2 Tree Sculpture. The issue of moving the large branches is not yet resolved. The working group is adamant that this should be paid for by BCC at it would have had to remove everything if the tree had been felled. Carry forward. Action: Gary to look for a solution. Carry forward to next meeting. Afternote: Tree sculpture completed on 25th May 2016.
1.3Japanese Knotweed Flier. This has been approved by BCC. Could add the NP and BCC logos. It needs to be distributed around the affected houses in the area. It should also be sent to Alan Aburrow for the website and to OSPNR for their website. Also to go in local noticeboards. Action: Gary
1.4Work on PROWs part-funded by the NP. This is now complete.
1.5Roman Villa information board. The design has been done. It needs a little –re-jigging and a larger font size. Action: Gary and Alan Afternote: Information board has been re-jigged according to the suggestions given.
1.6Westbury in Bloom. Hilary mentioned that there is now a team of four volunteers working on Westbury in Bloom following Sue’s retirement from the role
2. Ebeneezer Lane
2.1There has been on-going correspondence on this matter between residents and BCC. Duncan Venison from BCC Highways attended the meeting to discuss this matter.
2.2The current schedule is for two cuts per year (June and September). The proposal to go to one per year would mean the cut being performed in September. The Maintenance team deals with all of these cuts. Whilst it may be possible to go to one per year there is a concern that if complaints are received this will mean an extra cost scheduling in an unplanned cut. It is possible to go to one cut. Duncan said he would consider it and get back to the group.
2.3Why not trial it for a year? The first year is unlikely to be a problem but it may become a problem in future years. The issue for BCC is the cost of extra cuts (probably in July).
2.4If we go to one cut per year, the spare capacity could be used elsewhere (Hollybush Lane) where more cuts are needed.
2.5It is acknowledged that trees shouldn’t be cut by the strimmers cutting back the lane. There has been some tree work performed on the Stoke Lodge side of the lane. This isn’t performed by BCC contractors. 2.6 Cyclists should not be using the footpath. Obviously it’s very hard to catch them at it. This is a police enforcement matter. A sign could be put up but it is known that these have limited impact.
2.7There has been an increase in Japanese Knotweed on the path. Do contractors know what to do with this? It has to be dealt with under strict guidelines.
2.8Duncan will send an email response regarding all the issues raised
3.0Neighbourhood Partnership Plan
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Stoke Bishop, Westbury-on-Trym and Henleaze Neighbourhood Partnership at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
Neighbourhood Coordinator's reportResolved – that 1. The three recent forums be noted; 2. The current budget of the NP be noted; 3. The meeting schedul...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.