Item18
Resolved
Resolved (9 for, 0 against, 1 abstention) that the application be approved as per the recommendations contained in the report and including changes set out in the Amendment Sheet, together with the following additional changes: (1) an amendment to condition 14 to include an additional sentence which will require scheme of mitigation to be submitted and implemented within a specific timescale if emissions exceed those predicted in the air quality assessment; (2) an additional condition requiring a phasing plan which will address members’ concern about the need to ensure the proper amount of battery storage is built out in conjunction with the gas generators.