Bishopston, Cotham and Redland Neighbourhood Partnership noted this item on Monday 23 January 2017. Below is the council's own wording, with the papers it was decided on.
Resolved by the Neighbourhood Partnership: (1) that the current budget of the NP be noted; (2) that the latest meeting schedule of dates for Forums and NP meetings in 2016/17 be noted subject to a decision on future NP meetings being made under Agenda Item 10 (Date of Next Meeting); (3) that the brief update regarding the Corporate Strategy be noted along with discussions regarding potential future governance models; (4) that the recently launched Clean Streets Campaign is noted; (5) that the recent case study report regarding the new playground at Ashley Green Park be noted; (6) ( unanimously ) £5,000 Transformer’s Youth Fund is accepted and administered through the small grants process as per the conditions within the report Resolved by the Neighbourhood Committee: (unanimously) that £84,595.16 worth of Section 106 funds are released for the new playground in Ashley Green Park. Action: Andrew McGrath
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Report to Bishopston, Cotham and Redland Neighbourhood Partnership
Bishopston, Cotham and Redland NEIGHBOURHOOD PARTNERSHIP
Monday 23rd January 2017
Report of: Andrew McGrath – Communities & Neighbourhoods
Title: Neighbourhood Co-ordinator
Contact Telephone Number: 0117 9036436
RECOMMENDATIONS. The NP is asked:
1. To note the current budget of the NP 2. To note the latest meeting schedule of dates for Forums and NP meetings in 2016/17 and to advise the Coordinator of any changes that need to be made 3. To note the brief update regarding the Corporate Strategy 2017-22 and discussions regarding potential future governance models 4. To note and comment on the recently launched Clean Streets Campaign, and to agree how the NP can progress its involvement in this campaign (see also the Street Scene Group’s report) 5. To note the case study report regarding the new playground in Ashley Green Park and to agree the release of £84,595.16 S106 funds held by this NP to pay for the playground 6. To accept £5000 Transformer’s Youth Fund and administer through the small grants process as per the conditions within the report. Decisions to be agreed by the whole Neighbourhood Partnership (see also the small grants report) 1. Budget update
Please see appendix 1. As the NP knows, the general budgets of the NPs have been frozen and are extremely unlikely to be returned. We can make no more financial commitments from our general budget.
CIL and S106 are not frozen. At the last NP meeting, this NP committed all of its CIL to the three projects outlined in the budget. It so happens that another small CIL amount (£223.48) has since been added to our CIL list. The NP may wish to discuss and agree what to recommend the Neighbourhood Committee allocate this amount to.
The NP has also been allocated £10,671.54 S106 funding for the provision of improvements to Parks and Open Spaces within one mile of the former Kings Arms (Kingsdown). The NP has one more NP scheduled before the demise of the current structure. The NP may wish to discuss and agree what to recommend the Neighbourhood Committee allocate this amount to (see Parks report).
The table below outlines what each working group has committed/spent against its spend limit. The figures match those in the budget update
Working Spend limit Notes Group for 2016/17 Street Scene £16,973.50 £5,000 2016/17 + £2,083.50 c/f approved at the April NP for 2016/17 + £3,000 for Kingsdown – (June NP) +£6,890 (Oct NP) Sustainable £37,000 £30k for Sommerville Rd project, Travel £3,000 committed (June NP) Trees £7,782 All committed
Young People £1,000 c/f from 2015/16. Overseen by C&E working group. Not spent Communication £3,250 £2,500 committed to community fair & Engagement costs at June NP (inc £2,100 for small grants process) Parks £57,842 £48,342 approved and committed (inc £7,842 RCAS play equipment) Small Grants £25,000 £18,494.44 allocated at June and Oct NPs TOTALS £148,847.50 Agreed expenditure = £127,091.94 2. Future meeting dates Please note the dates for upcoming meetings. The NP is asked to agree or amend the dates
Follow Bishopston, Cotham and Redland Neighbourhood Partnership at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Previous MeetingResolved – that the minutes of the above meeting be approved as a correct record and signed by the Chair subject to t...
Neighbourhood Co-ordinator's ReportResolved – that (1) the current budget of the NP is noted; (2) the brief update be noted relating to parks’ schemes i...
Minutes of the Previous MeetingResolved – that the above Minutes be approved as a correct record and signed by the Chair subject to the following al...
Sustainable Transport Working GroupResolved (unanimously) – that the Cabot Clifton and Harbourside Neighbourhood Partnership be requested to fund the co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.