RESOLVED – That the progress made to date against the Bundred review and the 2016-17 AGS action plans be noted and acknowledged.
Audit Committee noted this item on Thursday 25 January 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the progress made to date against the Bundred review and the 2016-17 AGS action plans be noted and acknowledged.
The Audit Committee acknowledge progress made to date against the Action Plan and consider any issues arising.
The 2016/17 Annual Governance Statement and Bundred review identified a number of issues that needed to be addressed to ensure continuous improvement in the governance framework, financial and budget management, and the process for managing the achievement of savings .
The improvements identified have been incorporated into a separate Annual Governance Statement Action Plan to be regularly monitored in 2017/18 and progress reported to the Audit Committee.
Page 1 of 26 1. Purpose
1.1To report on progress made to date against the Annual Governance Action Plan arising from the Bundred Review and the 2016/17 Annual Governance Statement.
2.1The members of the Audit Committee previously endorsed, in their meeting on 23rd June 2017, that the Committee should receive monitoring reports at each of its meetings advising of progress against the Annual Governance Statement Action Plan.
2.2The progress made to date against the implementation of the agreed actions arising from the Councils response to the Bundred review is summarised below and details are attached in Appendix A.
Table 1 - Changes in the Implementation of Actions from the Bundred Review
Status January 2018 November 2017
Green – Completed and Evidenced 55 (65%) 52 (61%)
Amber – In Progress with Evidence 29 (34%) 33 (39%)
Red – Not Started / Started but not 1 (1%) 0 (0%) Evidenced, date at risk Total 85 85
2.3Since the previous report to the Audit Committee in November 2017, the principal changes in the implementation of the Bundred review have been:
B18 – Decision Pathway -- Amber to Red B35 – Learning and Development Programme – Amber to Green B45 – Development of Target Operating Model – Amber to Green B49 – Challenge and Monitor number of officers at meetings – Amber to Green
2.4The progress made to date against implementation of the actions required from the Annual Governance Statement for 2016/17 is summarised below and the details attached in Appendix B:
Table 2 - Changes in the Implementation of Actions from the Annual Governance Statement
Status January 2018 November 2017
Green – Completed and Evidenced 4 (18%) 4 (18%)
Amber – In Progress with Evidence 18 (82%) 18 (82%)
Red – Not Started / Started but not 0 (0%) 0 (0%) Evidenced, date at risk Total 22 22
Page 2 of 26 3. Proposal
3.1The Audit Committee considers the progress made to date against the Action Plan and consider any issues arising and raising challenge where appropriate.
4. Other Options Considered – N/A
5. Risk Assessment
5.1The publication of an Annual Governance Statement is a legal requirement and the processes of implementation, monitoring and reporting of improvement actions arising therefore constitute an important element of the Council’s governance arrangements. The actions identified within the response to the Bundred report and the Annual Governance Statement constitutes important measures whereby the Council’s overall management of organisational risk can be enhanced.
6. Public Sector Equality Duties
6.1Before making a decision, section 149 Equality Act 2010 requires that each decision-maker considers the need to promote equality for persons with the following “protected characteristics”: age, disability, gender reassignment, pregnancy and maternity, race, religion or belief, sex, sexual orientation. Each decision-maker must, therefore, have due regard to the need to:
i) Eliminate discrimination, harassment, victimisation and any other conduct prohibited under the Equality Act 2010.
ii) Advance equality of opportunity between persons who share a relevant protected characteristic and those who do not share it. This involves having due regard, in particular, to the need to --
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Bundred report and Annual Governance Statement trackerReport | 815 KB | DownloadRead as text |
Follow Audit Committee at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 28 May 2026 | Minutes of Previous Meeting held on 24th March 2026RESOLVED – that the minutes of the meeting held on 24 th March 2026 be approved as a correct record and signed by the... | Approved | Open |
| 28 May 2026 | Work ProgrammeRESOLVED –that thereport benoted. | Decided | Open |
| 28 May 2026 | Internal Audit Annual Report 2025/26Decision Notices would be subject to reaudit in the first half of 2026/27. ACTION: Officersto (1)improve accessibilit... | Decided | Open |
| 28 May 2026 | Annual Fraud Report 2025/26Resolved – That the annual fraud report be noted. | Noted | Open |
| 28 May 2026 | Draft Annual Governance Statement 2025/26Resolved (unanimously) – That the Annual Governance Statement be approved subject to the amendments and clarification... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.