That the Public Forum question (whether the proportion of locally allocated CIL funds can be increased from 15%) will be reviewed. There was a discussion surrounding accessibility of relevant information related to the CIL process for citizens and whether elected Members are appropriately informed. That there is a need for updated guidance on the process, and that Member briefings would be helpful. There was a discussion about delivery timetables, and Officers stated that there was not a fixed timetable as it depended on the capacity of the Parks and Transport departments. It be noted that (i) as a result of consultation, project resources for Parks will be increased and a schedule will be published when it is clear that there will be enough capacity to enable delivery; and (ii) there is now an agreement in place with Transport and Parks departments to share a tracker for all schemes; that elected Members will receive a status report twice yearly; and there will be further updates should there be changes to existing plans. A Member stated that there should be flexibility and a facility for different processes for different levels of funding requested; that the existing model may prevent release of money for a publicly supported project in need of speedy approval. Vice-Chair of Communities Scrutiny Commission will make proposals to the Commission of an appropriate process to resolve this issue without using extra Officer resource .
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
That Communities Scrutiny Commission consider the results of the review of the first year of operation of the Area Committee local Community Infrastructure Levy (CIL) and Section 106 (S106) decision-making process 2018 and comment on the improvements which are being delivered in the 2019 process set out in the report and the appendices .
1 Communities Scrutiny Commission Date 14th January 2019 – Community Infrastructure Levy (CIL) & S106 - update and review of the new Area Committee arrangements
Summary
The 2018 Area Committee local CIL and S106 decision-making process was developed and delivered to carry through the resolution approved by Full Council on 20 th March 2018. It has delivered its first year of decisions through Area Committees. This report describes the results, the learning from this first year and the proposed improvements to the process for 2019.
2. Context
i. 6 Area Committees were created at the Full Council 20th March 2018. Their purpose is to take decisions over spend of the local element of CIL (15% of the total CIL allocation) and devolved S106 where there is a decision to be made about what and or where the s106 is spent.
ii. The committees will meet once a year with the option of an additional meeting where required and will be supported by Democratic Services.
iii. The 2018 decision-making process was delivered in 3 Stages between February – November 2018, resulting in £1,831,162 of funds being approved by Area Committees to deliver 45 projects, using both local CIL and S106 monies
iv. A review of the 2018 process was started in late September, involving Chairs of the 6 Area Committees and an online survey
v. The results have been used to shape an improved timeline and process for 2019 to reflect the suggestions and views emerging from the review.
vi. A report of the learning review will be available on the council website in January 2019.
vii. Area Committee Terms of reference and guidance about the process is available on the BCC website. [https://www.bristol.gov.uk/documents/20182/32767/CIL+and+S106+funding+guidance/2eb38 5d6-c933-7f0d-6d59-dcb7b8e6f2a2]
viii. The Strategic element of CIL (85%) is to be applied to infrastructure schemes that support the growth identified in the Local Plan. This could be items such as a new school, major highway works, a new railway station etc. The purpose of these allocations is that they help to deliver major infrastructure that either unlocks or supports the delivery of strategic growth in Bristol.
ix. Government guidance on the Strategic element of CIL states as follows:
Local authorities must spend the levy on infrastructure needed to support the development of their area, and they will decide what infrastructure is needed.
2 Communities Scrutiny Commission Date 14th January 2019 – Community Infrastructure Levy (CIL) & S106 - update and review of the new Area Committee arrangements
This flexibility gives local areas the opportunity to choose what infrastructure they need to deliver their relevant Plan (the Local Plan in England, Local Development Plan in Wales, and the London Plan in London). Charging authorities may not use the levy to fund affordable housing.
The Senior Responsible Officer in respect of the spending of the strategic component of CIL is Zoe Willcox (Director of Development). Potential allocations are initially considered by the Growth & Regeneration Board, before being taken to Cabinet for a formal decision to allocate funding to a specific project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.