Resolved
Resolved – (Voting 6 for, 3 against) that the application be refused. Councillors Shah and Smith left the Meeting.
Planning Committee A refused this item on Wednesday 22 January 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – (Voting 6 for, 3 against) that the application be refused. Councillors Shah and Smith left the Meeting.
Development Control Committee A – 22 January 2020 ITEM NO. 2
WARD: Southville
SITE ADDRESS: St Catherines Place Shopping Centre East Street Bedminster Bristol BS3 4HG
APPLICATION NO: 18/05310/F Full Planning
DETERMINATION 27 March 2019 DEADLINE: Full planning application for comprehensive redevelopment of the site to provide mixed use development comprising 205 residential dwellings (Class C3), 1288sqm of new retail, leisure and commercial space including a cinema (Class A1, A3, D2), refurbishment of existing retail facilities together with parking and amenity space, vehicular access, servicing arrangements, public realm, landscaping and associated works. (Major).
RECOMMENDATION: Refuse
AGENT: GVA APPLICANT: Firmstone Consortia One Limited St Catherine's Court C/o Agent Berkeley Place Bristol BS8 1BQ
The following plan is for illustrative purposes only, and cannot be guaranteed to be up to date.
LOCATION PLAN:
13/01/20 16:16 Committee report Item no. 2 Development Control Committee A – 22 January 2020 Application No. 18/05310/F: St Catherine’s Place Shopping Centre East Street Bedminster Bristol BS3 4HG
INTRODUCTION
This is an update to the Committee Report and Amendment Sheet presented to Development Control Committee A on 20 November 2019. At the meeting of DC A Committee on 20 November 2019, the motion passed was:
“Resolved – that a decision on the application be deferred until a future meeting of the Committee to allow time for transport and other minor issues to be resolved.”
The Committee Report for the meeting on 20 November is attached to this Report as a supporting document.
Members must consider the whole application on its merits against all of the relevant policies and all material planning considerations. Members therefore, should not and cannot confine their consideration of the application to the transport and other minor issues.
UPDATE
Further meetings have been undertaken between the applicant and Transport Officers, where it is now confirmed by Transport Development Management (TDM) that their previous concerns as reported in November 2019 have now been adequately addressed subject to conditions and appropriate s.106 obligations. The detailed response from TDM to the application is a supporting document to this Report.
The Officer's recommendation in this case is to refuse planning permission.
This is for one reason:
1. The proposed development by reason of its height, scale, massing, inadequate public realm and overall design quality, would be unacceptable in design terms and impact on existing residential amenity. This would be contrary to Section 12 of the National Planning Policy Framework (February 2019); Policy BCS21 of the Bristol Core Strategy (June 2011); Policies DM26, DM27, DM28 and DM29 of the Site Allocations and Development Management Policies (July 2014); Urban Living SPD (November 2018); and Bedminster Green Framework (March 2019).
THE APPLICATION
The application seeks full planning permission for the construction of: A total 205no. residential dwellings contained within 5no. ‘development blocks’ (Blocks A-E) 844sqm GIA of new build commercial floorspace including a new cinema (Use Classes A1, A3, D2) Refurbishment and reformatting of existing retail facilities (2,500sqm) 27no. car parking spaces (of which 12 are disabled parking spaces) 395no. cycle parking spaces: 343 for the residential dwellings and a further 52 cycle parking spaces for the commercial floorspace/visitors New public realm and hard/soft landscaping Item no. 2 Development Control Committee A – 22 January 2020 Application No. 18/05310/F: St Catherine’s Place Shopping Centre East Street Bedminster Bristol BS3 4HG
The dwellings proposed within the scheme would comprise of: 76no. 1 bedroom, 2 person dwellings 8no. 2 bedroom, 3 person dwellings 114no. 2 bedroom, 4 person dwellings 7no. 3 bedroom, 5 person dwellings
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
18/05310/F: St Catherine's Place Shopping Centre, East Street, BedminsterReport | 7 MB | DownloadRead as text |
Follow Planning Committee A at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jul 2026 | Minutes of the previous meetingRESOLVED – That the minutes of the previous meeting be approved as AMENDED, as a correct record. | Approved | Open |
| 22 Jul 2026 | AppealsRESOLVED – That the report was NOTED. | Noted | Open |
| 22 Jul 2026 | EnforcementRESOLVED – That the report was NOTED. | Noted | Open |
| 22 Apr 2026 | Minutes of the previous meetingRESOLVED (unanimously) – That the minutes of the previous meeting be approved as AMENDED, as a correct record, and si... | Approved | Open |
| 22 Apr 2026 | AppealsRESOLVED – that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.