Resolved
Resolved – (Voting 7 for, 0 against) that the application be granted subject to the inclusion of a condition concerning a specifically marked cycle route.
Planning Committee B decided this item on Wednesday 18 March 2020. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved – (Voting 7 for, 0 against) that the application be granted subject to the inclusion of a condition concerning a specifically marked cycle route.
The application in front of Members is for a new Household Recycling and Reuse Centre (HRRC) on the site of the current street cleaning depot set back from Hartcliffe Way. The background to which stems from Bristol's Waste and Resource Management Strategy" (April 2016) which makes a commitment to address the inadequacy of the current Household Recycling and Reuse Centres (HRRC) in the city. In 2017 money was allocated into the Capital Program to develop such a facility.
A Household Waste Recycling Centre (HWRC) was previously given permission on this site (application reference: 12/05168/F) but was not implemented at the time. The site is within a designated Principal Industrial and Warehousing Area (PIWA). The adjoining site to the site to the south has an allocation (BSA1119) within the Local Plan for Industry and Warehousing or a HWRC.
Following the provision of additional information, as set out in the following report, the proposal is considered acceptable on use; visual impact; nature conservation; arboriculture; noise; pollution; flood risk; sustainability; security; and contamination grounds.
In order to ensure that the facility does not cause significant highway safety consequences on Hartcliffe Way, a new traffic lighted junction is proposed. This will obviously have a noticeable impact on traffic movement in the immediate area, however Transport Development Management consider that with the range of measures secured through conditions and obligations the impact will be adequately mitigated. Further it will provide a pedestrian crossing better linking both sides of Hartcliffe Way (including if further housing comes forward in the locality).
As such, the proposals accord with the most of the relevant policies within the existing Bristol Local Plan as detailed below subject to conditions and financial obligations again set out below.
However, the area where there is not full compliance with the Local Plan is in respect of Air Quality.
The proposal would result in a predicted decrease in air quality arising from traffic generated by the development at receptors at the Parson Street gyratory to include Parson Street School which cannot be adequately mitigated. This issue is fully set out in Key Issue D.
Members are thus advised that the air quality impacts of the proposed development are considered significant and BCC Air Quality Team maintain an objection to the application.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
19/05204/F: 83 Hartcliffe Way Bristol BS3 5RNReport | 9.6 MB | DownloadRead as text |
Follow Planning Committee B at Bristol and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 1 Apr 2026 | Minutes of the previous meetingResolved – That the minutes of the 24 February 2026 be agreed as a correct record of the meeting and signed by the Ch... | Agreed | Open |
| 1 Apr 2026 | 25/10013/P - Land Next To River Cattle Market Road Bristol BS1 6QWResolved (Unanimous) - That the application be granted subject to conditions. | Decided | Open |
| 1 Apr 2026 | 25/12231/FB - Kings Weston Avenue Open Space Footpaths Bristol BS11Resolved (5 for, 4 against) - That the application be approved subject to Planning Agreement. 10. Date of next meetin... | Approved | Open |
| 30 Apr 2025 | Minutes of the previous meetingResolved – that the minutes of 12 March 2025 be agreed as a correct record. | Agreed | Open |
| 30 Apr 2025 | 24/05143/F - Premier Business Park Sussex Street BristolResolved –That the application be Granted subject to S106 Planning Agreement and conditions as set out in the report ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.