Overview and Scrutiny Management Board agreed this item on Tuesday 14 February 2023. Below is the council's own wording, with the papers it was decided on.
It was agreed that questions related to Service Areas would be directed to relevant officers for a written response. In relation to a previously raised point a Member noted that the average amount of carbon emitted in the construction of a home is 50 tonnes and queried whether the figures for C02 emissions from the Council included the amount from construction. The Chief Executive stated that this would not be in scope 1 and 2 which were emissions set for the City, however it was felt that the emissions from construction were part of a conversation of wider decarbonisation which had begun internally but was not being measured. ACTION: That written responses to performance questions related to service areas be provided.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
That OSMB note the progress to date made against delivering the Priorities within the 7 Themes in the BCC Corporate Strategy 2022-27 and Business Plan 2022/23, and that Scrutiny members identify areas of specific interest or concern to review progress (positive or negative) with relevant Managers or Directors.
The significant issues in the report are:
This is a new approach to performance reporting, and includes a performance progress report with detailed data appendices for each of the 7 Themes in the BCC Corporate Strategy.
Of the overall Performance Metrics and Actions reported this quarter: • 50% of Q2 Business Plan Priority Measures are on or better than target (27 of 54) • 62% of Q2 Business Plan Priority Measures have improved (26 of 42) • 78% of Q2 Business Plan Actions are currently on track or better (67 of 86) Overview and Scrutiny Management Board – Quarterly Performance report
1. Background context
Performance reporting is now based on the Bristol City Council (BCC) Corporate Strategy 2022-27. This report and appendices provide the relevant Performance Measures from the Business Plan 2022/23, as approved by CLB in Feb and noted by Cabinet in March 2022. Key points of note: Thematic Performance Clinics (TPCs) - As per the Performance Framework 2022/23, reporting is primarily through new Thematic Performance Clinics, which focus on overall Performance for each of the 7 Business Plan themes, and address specific Performance Improvement issues for that theme. Business Plan Actions – for the first time, Performance reporting includes progress of the Business Plan Actions as well as Performance Metrics. This allows more focus on delivery of the Business Plan Priorities. Business Plan Priority Measures / City Outcomes – The quarterly reports focus on Business Plan Priority Measures (mainly quarterly measures centred on the Corporate Strategy priorities; primarily metrics the council has more direct responsibility over, so used to measure council performance). Where relevant they’ll note City Outcomes (annual indicators on the Corporate Strategy themes and overall ‘health of the city’; primarily outcome-focused measures that are longer term and slow moving, with long-term targets); these will all be in the Annual report. Impact of Covid-19 – Covid-19 renewal and recovery is embedded into our Business Plan Priorities and is being delivered across all areas of the council. Targets are set to take account of this, including some which may appear counter-intuitive compared to last year’s outturn (see 2022/23 Performance Measures and Targets).
Summary
Overall Performance summary: Taking the Business Plan Performance metrics and Actions available this quarter: City Outcomes Business Plan Actions Business Plan Priority Metrics (mainly annual metrics) Current Performance 50% on target or better 100% on target or better 78% on track or better (67/86) (27/54) of those with targets (8/8) of those with targets Direction of Travel 6% better than Q1 (5/86) 62% improved compared to 12 75% improved compared 83% same as Q1 (71/86) months ago (26/42) to 12 months ago (6/8) 12% worse than Q1 (10/86) Overview and Scrutiny Management Board – Quarterly Performance report
Q2 Actions by Theme and Status (86 Actions, 78% on track or better ) 73% 87% 18 on track+ on track+ 69% 16 92% (11/15) (13/15) on track+ on track+ 14 82% (9/13) 1 40% (12/13) 1 on track+ 100% Number of Actions
1 on track+ 12 (9/11) on track+ (4/10) 10 (9/9)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Minutes of the previous meeting.RESOLVED; That the Minutes from the OSMB meeting held on 4 th December 2023 be published and approved at the next OSM...
Mayor's Forward Plan - Standing ItemIt was agreed that a statement on this would be included in the submitted referral to Cabinet. RESOLVED; That the May...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.