That Cabinet: 1. Approved the Full Business Case at Appendix A and exempt appendix I and the allocation of the capital budget up to £980,000, to support the delivery of the refurbishment of the city centre flats. 2. Approved the assignment of a property lease from a Registered Provider of Social Housing, pending a satisfactory property review to confirm the costs set out in the Full Business Case (£980,000). 3. Authorised the Executive Director – Growth and Regeneration in consultation with Cabinet Member with responsibility for Housing Delivery and Homelessness and the Director of Finance (S151 Officer) to take all steps required to negotiate the assignment of the property lease and procure and award contracts (which may be over the key decision threshold) for the refurbishment of the city centre flats for use as TA. 4. Authorised the Executive Director – Growth and Regeneration in consultation with Cabinet Member with responsibility for Housing Delivery and Homelessness and the Director of Finance (S151 Officer) to take all steps required to negotiate the extension of the lease with the Hospital Trust, to maximise savings through the continued use of the 24 flats for TA.
Word for word from the decision Bristol published for this meeting.Source: democracy.bristol.gov.uk
Ward(s) Citywide Author: Paul Sylvester Job title: Head of Housing Options Cabinet lead: Councillor Tom Renhard, Cabinet Executive Director lead: John Smith, Interim Executive Director Member for Housing Delivery and Homelessness Growth and Regeneration Proposal origin: BCC Staff Decision maker: Cabinet Member Decision forum: Cabinet Purpose of Report: 1. To approve the Full Business Case (FBC) for the conditional assignment of a property lease from a Registered
Provider of Social Housing and to conditionally approve the release of £980,000 of capital funding
2. To update cabinet on plans to extend the lease with the Hospital Trust for 24 units of accommodation (see
previous cabinet paper Cabinet 1 November 2022 Temporary Accommodation Partnership) and seek
delegated authority for Executive Director for Growth and Regeneration to negotiate the extension of the
lease.
1. Evidence Base:
2. Lease of 10 flats from a Registered Provider of Social Housing
3. As of March 2023, there were 105,000 households living in temporary accommodation (TA) across England,
including 131,000 children. In 2010, there were only 49,580 households in TA. According to research from
Shelter published in January 2023 the number of people identified as living in temporary accommodation had
risen by an alarming 74% in the last 10 years. Of that total, more than two-thirds had been living in
temporary accommodation for more than a year.
4. Many local authorities are feeling the impact of this locally and Bristol is no different. In Bristol, demand has
1 Version May 2023
OFFICIAL continued to grow and there are now over 1,400 households in TA. The council has a legal obligation to
house people who are legally homeless and vulnerable. Due to a lack of affordable housing much of that
accommodation is secured via expensive spot purchased accommodation from the private rental sector. The
council claims some of the cost back via Housing Benefit, but this is capped by central government, linked to
Local Housing Allowance (LHA) rates set in 2011, so the amount that the council pays above the cap results in
a loss to the council, known as subsidy loss.
5. The annual TA subsidy loss for 2024/25 is estimated to total over £17m if no steps were taken to reduce this
cost. Long-term, the solution to high numbers of households in TA is to increase the amount of general needs
affordable housing available and so we are working with our Housing Revenue Account (HRA) and Registered
Provider (RP) partners to identify opportunities to increase our housing stock at pace. In the short-term we
are working on various workstreams to reduce our dependence on expensive private-rented TA to reduce our
subsidy loss.
6. Without transformation, continuing to work ‘as-is’ will simply see an increase in subsidy loss to the council as
demand increases.
7. An opportunity has arisen to explore taking a lease (c.10 years) for a city centre building containing 10 ex-
student flats for conversion and use as temporary accommodation (TA) – potentially a replica of the ‘hospital
trust’ project, though over a longer period.
8. The building contains 34 bedrooms, and on first consideration, based on generating savings by moving
people out of the most expensive accommodation we use for TA under the current Emergency
Accommodation (EA) Framework, it could generate c. £237k per year (recurring) in subsidy loss savings.
9. These flats will be used for households who we have a duty to provide with temporary accommodation.
These households will be registered with the council and nominated to occupy the flats until they are able to
move on into settled longer-term accommodation, for example, into a private renting or a social tenancy.
BCC will commission support for each household for the duration of their stay. They will be supported in
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Safety Valve Programme – capital fundingThat Cabinet: 1. Noted the full terms of the Safety Valve agreement with the Department for Education (DfE) (Appendix...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.